North Carolina Administrative Code
Title 04 - COMMERCE
Chapter 11 - UTILITIES COMMISSION
Chapter 8
Article 11 - RESOURCE PLANNING AND CERTIFICATION
Section 11 R08-61 - PRELIMINARY PLANS AND CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY FOR CONSTRUCTION OF
Current through Register Vol. 39, No. 6, September 16, 2024
(a) A public utility or other person that plans to build an electricity generating facility with a nameplate capacity of 300 megawatts (alternating current) or more shall file with the Commission and the Department of the Environment and Natural Resources its preliminary plans at least 120 days before filing an application for a certificate of public convenience and necessity. The preliminary plans shall include the following exhibits:
(b) In filing an application for a certificate of public convenience and necessity pursuant to G.S. 62-110.1(a) in order to construct a generating facility in North Carolina, a public utility shall include the following exhibits supported by relevant testimony:
(c) The public utility shall submit a progress report and any revision in the construction cost estimate during each year of construction according to a schedule established by the Commission.
(d) Upon the request of the public utility or upon the Commission's own motion, the Commission may conduct an ongoing review of construction of the generating facility as the construction proceeds.
(e) A public utility requesting an ongoing review of construction of the generating facility pursuant to G.S. 62-110.1(f) shall file an application, supported by relevant testimony, for an ongoing review no later than 12 months after the date of issuance of a certificate of public convenience and necessity by the Commission; provided, however, that the public utility may, prior to the conclusion of such 12-month period, petition the Commission for a reasonable extension of time to file an application based on a showing of good cause. Upon the filing of a request for an ongoing review, the Commission shall establish a schedule of hearings. The hearings shall be held no more often than every 12 months. The Commission shall also establish the time period to be reviewed during each hearing. The purpose of each ongoing review hearing is to determine the reasonableness and prudence of the costs incurred by the public utility during the period under review and to determine whether the certificate should remain in effect or be modified or revoked. The public utility shall have the burden of proof to demonstrate that all costs incurred are reasonable and prudent.
(f) A public utility may file an application pursuant to G.S. 62-110.6 requesting the Commission to determine the need for an out-of-state electric generating facility that is intended to serve retail customers in North Carolina. If need for the generating facility is established, the Commission shall also approve an estimate of the construction costs and construction schedule for such facility. The application may be filed at any time after an application for a certificate of public convenience and necessity or license for construction of the generating facility has been filed in the state in which the facility will be sited. The application shall be supported by relevant testimony and shall include the information required by subsection (b) of this Rule to the extent such information is relevant to the showing of need for the generating facility and the estimated construction costs and proposed construction schedule for the generating facility. The public utility shall submit a progress report and any revision in the construction cost estimate for the out-of-state electric generating facility during each year of construction according to a schedule established by the Commission.
(g) If the Commission makes a determination of need pursuant to G.S. 62-110.6 and subsection (f) of this Rule, the provisions of subsections (d) and (e) of this Rule shall apply to a request by a public utility for an ongoing review of construction of a generating facility to be constructed in another state that is intended to serve retail customers in North Carolina. An electric public utility shall file an application, supported by relevant testimony, for an ongoing review no later than 12 months after the date of issuance of a certificate of public convenience and necessity or license by the state commission in which the out-of-state generating facility is to be constructed; provided, however, that the public utility may, prior to the conclusion of such 12-month period, petition the Commission for a reasonable extension of time to file an application based on a showing of good cause.
(h) A public utility may file an application pursuant to G.S. 62-110.7 requesting the Commission to review the public utility's decision to incur project development costs for a potential in-state or out-of-state nuclear generating facility that is intended to serve retail electric customers in North Carolina. The application, supported by relevant testimony, shall be filed prior to the filing of an application for a certificate to construct the facility.
NCUC Docket No. E 100, Sub 54, 12/8/88; E-100, Sub 78A, 04/29/98; NCUC Docket No. E-100, Sub 113, 02/29/08; NCUC Docket No. E-100, Sub 134, 07/30/12; NCUC Docket No. M-100, Sub 135, 09/10/13; NCUC Docket No. E-100, Sub 134, 11/04/14.