North Carolina Administrative Code
Title 04 - COMMERCE
Chapter 11 - UTILITIES COMMISSION
Chapter 8
Article 10 - FUEL BASED RATE CHANGES
Section 11 R08-55 - ANNUAL HEARINGS TO REVIEW CHANGES IN THE COST OF FUEL AND FUEL-RELATED COSTS
Current through Register Vol. 39, No. 6, September 16, 2024
(a) As used in this rule, "cost of fuel and fuel-related costs" means all of the following:
Cost of fuel and fuel-related costs shall be adjusted for (a) any net gains or losses resulting from any sales by the electric public utility of fuel and other fuel-related costs components and (b) any net gains or losses resulting from any sales by the electric public utility of by-products produced in the generation process to the extent the costs of the inputs leading to that by-product are costs of fuel or fuel-related costs.
(b) For each electric public utility generating electric power by means of fossil and/or nuclear fuel for the purpose of furnishing North Carolina retail electric service, the Commission shall schedule an annual public hearing pursuant to G.S. 62-133.2(b) in order to review changes in the electric public utility's cost of fuel and fuel-related costs. The annual cost of fuel and fuel-related cost adjustment hearing for Duke Energy Carolinas, LLC, will be scheduled for the first Tuesday of June each year; for Duke Energy Progress, LLC., the annual hearing will be scheduled for the third Tuesday of September each year; and for Virginia Electric and Power Company, d/b/a Dominion Energy North Carolina, the annual hearing will be scheduled for the third Tuesday of November each year.
(c) The test periods for the hearings to be held pursuant to paragraph (b) above will be uniform over time. The test period for Duke Energy Carolinas, LLC will be the calendar year; for Duke Energy Progress, Inc., the test period will be the 12-month period ending March 31; and for Dominion North Carolina Power, the test period will be the 12-month period ending June 30.
(d) The Commission shall permit each electric public utility to charge an increment or decrement as a rider to its rates for changes in the cost of fuel and fuel-related costs used in providing its North Carolina customers with electricity from the cost of fuel and fuel-related costs established in the electric public utility's previous general rate case on the basis of cost per kilowatt-hour. The increment or decrement may be different among customer classes. The general methodology and procedures to be used in establishing the cost of fuel and fuel-related costs shall be as follows:
(e) Each electric public utility, at a minimum, shall submit to the Commission for purposes of investigation and hearing the information and data in the form and detail as set forth below:
An electric public utility that is subject to G.S. 62-133.2(a3) is required to provide only the applicable information prescribed by subdivisions (5), (6) and (8) of this subsection.
(f) The electric public utility shall file the information required under this rule, accompanied by workpapers and direct testimony and exhibits of expert witnesses supporting the information filed herein, and any changes in rates proposed by the electric public utility (if any), not less than 98 days prior to the hearing; . Nothing in this rule shall be construed to require the electric public utility to propose a change in rates or to utilize any particular methodology to calculate any change in rates proposed by the utility in this proceeding.
(g) The electric public utility shall publish a notice for two (2) successive weeks in a newspaper or newspapers having general circulation in its service area, normally beginning at least 30 days prior to the hearing, notifying the public of the hearing before the Commission pursuant to G.S. 62-133.2(b) and setting forth the time and place of the hearing.
(h) Persons having an interest in said hearing may file a petition to intervene setting forth such interest at least 21 days prior to the date of the hearing. Petitions to intervene filed less than 21 days prior to the date of the hearing may be allowed in the discretion of the Commission for good cause shown.
(i) The Public Staff and other intervenors shall file direct testimony and exhibits of expert witnesses at least 21 days prior to the hearing date. If a petition to intervene is filed less than 21 days prior to the hearing date, it shall be accompanied by any direct testimony and exhibits of expert witnesses the intervenor intends to offer at the hearing.
(j) The electric public utility may file rebuttal testimony and exhibits of expert witnesses no later than 12 days prior to the hearing date.
(k) The burden of proof as to the correctness and reasonableness of any charge and as to whether the test year cost of fuel and fuel-related costs were reasonable and prudently incurred shall be on the utility. For purposes of determining the EMF rider, a utility must achieve either (a) an actual system-wide nuclear capacity factor in the test year that is at least equal to the national average capacity factor for nuclear production facilities based on the most recent 5-year period available as reflected in the most recent North American Electric Reliability Corporation's Generating Availability Report, appropriately weighted for size and type of plant or (b) an average system-wide nuclear capacity factor, based upon a two-year simple average of the system-wide capacity factors actually experienced in the test year and the preceding year, that is at least equal to the national average capacity factor for nuclear production facilities based on the most recent 5-year period available as reflected in the most recent North American Electric Reliability Corporation's Generating Availability Report, appropriately weighted for size and type of plant, or a presumption will be created that the utility incurred the increased cost of fuel and fuel-related costs resulting therefrom imprudently and that disallowance thereof is appropriate. The utility shall have the opportunity to rebut this presumption at the hearing and to prove that its test year cost of fuel and fuel-related costs were reasonable and prudently incurred. To the extent that the utility rebuts the presumption by the preponderance of the evidence, no disallowance will result.
(l) The hearing will generally be held in the Hearing Room of the Commission at its offices in Raleigh, North Carolina.
(m) Each electric public utility shall follow deferred accounting with respect to the difference between actual reasonable and prudently incurred cost of fuel and fuel-related costs and cost of fuel and fuel-related costs recovered under rates in effect.
(n) If the Commission has not issued an order pursuant to G.S. 62-133.2 within 180 days after the date the electric public utility has filed any proposed changes in its rates and charges in this proceeding based solely on the cost of fuel and fuel-related costs, then the utility may place such proposed changes into effect. If such changes in the rates and charges are finally determined to be excessive, the electric public utility shall refund any excess plus interest to its customers in a manner directed by the Commission.
NCUC Docket No. E-100, Sub 47, 5/1/84; NCUC Docket No. E-100, Sub 47, 8/14/86; NCUC Docket No. E-100, Sub 55, 4/27/88; 6/22/88; 1/25/90; 12/11/90; NCUC Docket No. M-100, Sub 128, 10/27/99; NCUC Docket No. E-100, Sub 113, 2/29/08; NCUC Docket No. E-100, Sub 113, 3/13/08; NCUC Docket No. M-100, Sub 140, 12/03/13; NCUC Docket No. E-100, Sub 160, 10/11/18.