(a) The owner of a dam that been assigned a hazard classification of class B or C shall perform engineering assessments on a regular basis, as is set forth in this section.
(b) The department may require an engineering assessment from the owner of a dam that has been assigned a condition rating of "unsafe" or "unsound", based on the department's consideration of public safety and the specific characteristics of the dam and its location.
(c) All engineering assessments shall be performed on behalf of the owner by a professional engineer, who shall document the results of the inspection in an engineering assessment report, which shall be signed and sealed by the professional engineer.
(d) An engineering assessment shall be performed, and an engineering assessment report submitted to the dam safety section, at a minimum frequency of every 10 years for dams that have been assigned a hazard classification of class B or C.
(e) Unless a shorter time frame is imposed by the department in the interest of public safety based on the assignment of a condition rating of "unsafe" or "unsound" in accordance with section 673.16 of this Part, the schedule for submission of the first engineering assessment report is as follows.
(f) All engineering assessments shall include:
(g) All engineering assessment reports shall be retained by the dam owner and kept in good order.
(h) The department may review any engineering assessment report at any time to protect life, property or natural resources, may require additional information or clarification thereto, and/or may provide comments to be addressed in a revised engineering assessment report upon a finding that it was not prepared in compliance with this Part and/or generally accepted engineering practice in the field of dam design and safety. The owner shall revise the engineering assessment report to fully incorporate and/or resolve the department's comments and resubmit it to the department within 60 days of the owner's receipt of the department's comments, unless another time frame is either requested by the owner and agreed to by the department, or imposed by the department in the interests of public safety for a dam that has a condition rating of "unsafe" or "unsound".