Current through Register Vol. 46, No. 39, September 25, 2024
(a) Applicability.
This Part sets forth the requirements for commissioning of the mechanical plant
of a base building. This includes:
(1) those
systems, equipment and components of the mechanical plant that affect energy
consumption; and
(2) indoor air
quality systems, equipment and components that affect mechanical ventilation.
These commissioning requirements do not apply to the mechanical plant, if any,
of tenant space. These requirements do not apply to components that do not
affect the energy use of the building, such as safety controls.
(b) Commissioning process. The
owner must implement the commissioning process summarized below.
(1) Commissioning steps.
(i) Designate a qualified commissioning
authority (CA).
(ii) Ensure that
the:
(a) individuals or firms performing the
design of the base building or tenant space(s);
(b) the commissioning agent; and
(c) the commissioning authority fulfill their
roles and responsibilities in accordance with subdivisions (c) and (d) of this
section.
(2)
Systems to be commissioned.
(i) All base
building heating, ventilating, and air-conditioning (HVAC) systems, equipment
and components that affect energy use must be commissioned.
(ii) All indoor air quality systems that
affect the operation of the HVAC ventilation system of the base building must
be commissioned.
(iii) The
following list of systems, equipment and components must be commissioned:
(a) chillers, unitary and split-air
conditioners, boilers, furnaces, and domestic hot water and service hot water
heaters;
(b) cooling towers, fans,
pumps, heat exchangers;
(c)
controls for central plant and for HVAC, including, if present, the energy
management system or the portion of the building automation system (BAS) that
affects energy use;
(d) ducts and
associated dampers;
(e) piping and
associated valves;
(f) duct
insulation and pipe insulation;
(g)
duct system protection during construction, as related to indoor air
quality;
(h) air quality monitoring
systems as they relate to ventilation systems;
(i) renewable and alternative energy
technologies, as appropriate per mechanical plant definition;
(j) waste heat recovery; and
(k) thermal storage.
(iv) In addition to the systems, equipment
and components listed in subparagraph (iii) of this paragraph, other systems,
equipment and components that are used for heating, cooling, or ventilation and
that affect energy use or indoor air quality must also be
commissioned.
(c) Responsibilities of primary participants
in commissioning.
(1) Designers. The
individuals or the firms that design each system to be commissioned must
prepare in writing the following:
(i) design
intent;
(ii) basis of design;
and
(iii) full sequences of
operation for all equipment and systems, all of which must meet the
requirements of this Part and industry standards.
(2) Commissioning agent. The commissioning
agent must perform the functional testing of equipment, documented by the
commissioning authority, using forms approved by the commissioning authority,
all of which must meet the requirements of this Part and industry
standards.
(3) Commissioning
authority.
(i) The commissioning authority
must:
(a) develop a commissioning
plan;
(b) document performance
(i.e., determine and document whether systems, equipment and components are
functioning in accordance with the documented design intent and in accordance
with the construction documents);
(c) for the purposes of this Part, the
commissioning authority (CA) cannot be responsible for design concept, design
criteria, compliance with codes, design or general construction scheduling,
cost estimating, or construction management;
(d) review and approve the design intent,
basis of design, and sequence of operation. Commissioning authority approval is
solely for the purpose of ensuring that sufficient information is contained
therein to perform commissioning and must not constitute approval for any other
purpose; and
(e) develop, or assist
with developing and approve, or review and approve, the following written work
products:
(1) commissioning
specifications;
(2) commissioning
plan;
(3) start-up and check-out
checklists and procedures;
(4)
functional performance testing procedures and checklists;
(5) testing, adjusting, and balancing (TAB)
plan;
(6) operations and
maintenance manual;
(7) systems and
energy management manual; and
(8)
commissioning report.
Commissioning authority approval is solely for the purpose
of ensuring that the above are in accordance with the commissioning
requirements and must not constitute approval for any other purpose.
(4) Verify and document installation of
systems, equipment and components. This activity must ensure the following:
(i) that systems, equipment and components
are installed according to construction documents and manufacturer's
instructions;
(ii) that other
building systems or components are not compromising the efficacy of the systems
or features being commissioned; and
(iii) that any required differences between
the final installation and the original construction documents are
documented.
(5) Verify,
document, and approve that the start-up and checkout were completed and
performed as required by subdivision (h) of this section.
(6) Witness all or part of the HVAC piping
test and flushing procedure, sufficient to be confident that proper procedures
were followed. Document this testing and verify that this documentation is
included in operations and maintenance manuals. Notify owner of any
deficiencies in results or procedures.
(7) Witness all or part of any duct testing
and cleaning procedures, sufficient to be confident that proper procedures were
followed. Document this testing and verify that this documentation is included
in operations and maintenance manuals. Notify owner of any deficiencies in
results or procedures.
(8) Witness
sufficient functional testing of the control system and approve it to be used
for TAB, before TAB is executed.
(9) Verify, document, and approve that
functional performance tests were performed as required by this Part. See
subdivision (i) of this section for details.
(10) Maintain a master log for deficiencies
and resolutions, and maintain a separate testing record. Provide to the owner
written progress reports regarding issues related to the commissioning (e.g.,
progress being made, issues to resolve, milestones met, test results,
recommended actions).
(11) Review
the operations and maintenance manual for the completeness of all features
components, equipment, subsystems, and systems that are commissioned in
accordance with this Part.
(12)
Oversee and approve the training of the owner's operations and maintenance
personnel. See subdivision (j) of this section for details.
(13) Verify, document and approve required
seasonally- deferred testing and corrections of any deficiencies. Document
final testing and verify that this documentation is included in the
commissioning report and in operations and maintenance manuals.
(14) Return to the site between six months
and one year of building occupancy and review with facility staff the then
current building operation and all outstanding issues related to the original
commissioning and any seasonally deferred testing. Also interview facility
staff and identify problems or concerns they have with operating the building
as originally intended. Make suggestions for improvements and for recording
these changes in the operations and maintenance manual and in the systems and
energy management manual. Compliance with this paragraph is required before the
submission of the eligibility certificate for the second taxable year for which
the green building credit is claimed.
(d) Qualifications of the commissioning
authority and commissioning agent.
(1) The
commissioning authority's primary representative that will be fulfilling the
responsibilities of the commissioning authority must have a professional
engineer's license earned for mechanical engineering and must have a minimum of
five years of experience in HVAC engineering.
(2) The commissioning authority must approve
the qualifications of the commissioning agent.
(3) The commissioning agent and commissioning
authority may be the same organization or person.
(4) A qualified member of the architecture or
engineering firm or company that performs the design may act as the
commissioning authority; however, such an individual must not be responsible
for any aspect of the project design, or construction management or supervision
for the subject building. In addition, reporting of all conditions and findings
must be immediate and direct from the commissioning authority to the
owner.
(e) Design intent
and basis of design. A design intent narrative and a basis of design narrative
must be developed.
(1) An overall design
intent narrative is required for the following:
(i) space temperature and humidity
criteria;
(ii) thermal zoning
criteria;
(iii) level of occupant
control over HVAC systems (e.g., direct local control at the space level,
control only at a central energy management system level);
(iv) ventilation requirements and related
indoor air quality criteria;
(v)
performance criteria related to energy efficiency;
(vi) environmental responsiveness of the
facility; and
(vii) commissioning
criteria.
(2) The basis
of design must include at a minimum the following:
(i) occupancy;
(ii) space and process
requirements;
(iii) applicable
codes, policies, and standards;
(iv) design assumptions (e.g.,
heating/cooling load, and climatic);
(v) performance standards, benchmarks or
metrics;
(vi) interaction between
systems affecting intended performance; and
(vii) control system appropriate for the
skill of the operations and maintenance staff. The design intent and basis of
design must become part of the operations and maintenance manual and of the
systems and energy management manual.
(f) Commissioning plan.
(1) A commissioning plan covering a given
system, equipment or component is required before such system, element or
component is commissioned.
(2) The
commissioning plan must address the following:
(i) an overview of the tasks to be executed
during commissioning;
(ii) a list
of all features to be commissioned;
(iii) a list of reference documents related
to commissioning, including specification references, drawing list, and
submittal drawings;
(iv) a list of
primary participants in the commissioning process and their
responsibilities;
(v) a plan for
management, communication and documentation;
(vi) an outline of the scope of the
commissioning process, including submittal review, inspection, start-up,
testing, training, operations and maintenance manual, systems and energy
management manual;
(vii) a brief
description of the checklists and tests to be performed, with reference to
specific pre-start and start-up checklists;
(viii) a list of the functional performance
tests to be performed to verify proper operation of all commissioned systems,
including prerequisite activities and reference to specific checklists or
worksheets which are necessary;
(ix) where the commissioning authority is not
the commissioning agent, a description of the process to be performed by the
commissioning authority to verify that the systems are operating as indicated
in the documentation provided by the commissioning agent;
(x) a brief description of the content of the
training to be provided to the operations and maintenance personnel;
(xi) the expected written work products,
including checklist, worksheets, and testing procedures; and
(xii) an activity schedule.
(g) Commissioning
specifications.
(1) Commissioning
specifications must be included in the construction documents.
(2) The commissioning specifications must
include the following:
(i) scope and details
of the commissioning process;
(ii)
qualifications and skills required by the commissioning agent;
(iii) a detailed description of the
responsibilities of all parties included in the commissioning
process;
(iv) systems, equipment
and components to be commissioned;
(v) requirements for prefunctional checklist
and start-up;
(vi) the functional
performance testing process;
(vii)
specific functional performance test requirements, including testing conditions
and acceptance criteria for each piece of equipment being
commissioned;
(viii) provisions for
resolving deficiencies;
(ix)
requirements for reporting and documentation for commissioning;
(x) requirements for training;
(xi) requirements for operations and
maintenance manual, and for systems and energy management manual; and
(xii) schedule.
(h) Start-up and checkout.
Start-up and checkout must comprise the checks and tests to determine that all
components, equipment, subsystems, systems, and interfaces between systems
operate in accordance with construction documents. In this context, operate
includes all modes and sequences of control operation, interlocks and
conditional control responses, and specified responses to abnormal or emergency
conditions.
(1) The results of the start-up
and checkout must be documented and must be performed according to:
(i) the manufacturer's written instructions
for the systems and equipment being commissioned; and
(ii) the construction documents.
(2) A certificate of readiness
must be prepared by the contractor and delivered to the commissioning authority
stating that start-up and checkout have been successfully completed and that
all equipment, systems, and controls are complete and ready for functional
performance testing.
(i) The commissioning
authority must verify that initial start-up and checkout were successfully
completed.
(ii) The commissioning
authority must verify that every point of the control system was checked and
that every control point is commanding, reporting and controlling as specified
in the construction documents. Verification must include a minimum sample of
each type of control point. In addition, the controls that are verified must be
within a minimum sample of each type of component, equipment, subsystem and
system where the sensor type is installed. If any control point in the minimum
sample is not commanding, reporting and controlling as specified in the
construction documents, then an additional minimum sample of each type of
control found not to be performing must be checked, until all control points in
a minimum sample are found to be performing as specified.
(iii) The commissioning authority must verify
that all sensors have been calibrated so that the value reported in the control
system represents the actual local value. Verification must include
re-calibrating a minimum sample of each type of sensor. In addition, the
sensors that are re-calibrated must be within a minimum sample of each type of
component, equipment, subsystem and system where the sensor type is installed.
If any sensor in the minimum sample is out of calibration, then an additional
minimum sample of each type of sensor found to be out of calibration must be
re-calibrated, until all sensors in a minimum sample are found to be in
calibration.
(iv) The commissioning
authority must verify that all actuators have been adjusted to fully close and
open dampers and valves, and also must verify by visual observation that the
reported values in the control system are correct. Verification must include
checking the operation of a minimum sample of each type of actuator, valve, and
damper. In addition, the actuator, valve, and damper must be within a minimum
sample of each type of component, equipment, subsystem and system where the
type of actuator, valve, and damper is installed. If any actuator, valve, or
damper in the minimum sample does not operate as required in the construction
documents, then an additional minimum sample of each type of actuator, valve,
or damper found not to be operating as required must be verified until all
actuators, valves, or dampers in a minimum sample are found to be to be
operating as required.
(v) The
commissioning authority must verify the TAB by re-measuring a minimum sample of
values reported for each type of component, equipment, subsystem, or system in
the TAB reports. In addition, the values that are re-measured must be within a
minimum sample of each type of subsystem and each type of system. If any
re-measured value in the minimum sample deviates from the values in the TAB
report or from the requirements in the construction documents by more than 10
percent, then an additional minimum sample must be re-measured for each type of
component, equipment, subsystem or system for which there is a deviation, until
all re-measured values in a minimum sample are within 10 percent of the values
in the TAB report or of the requirements in the construction
documents.
(vi) The commissioning
authority must:
(a) check that chimneys,
chimney connectors and stacks are free of cracks, blockages and
leaks;
(b) ensure that proper
combustion air is provided to the HVAC equipment;
(c) ensure that all appliances are installed
in accordance with applicable fire safety and local building codes;
and
(d) witness the testing of
air-tightness of smoking areas (if any), and document that all air leaks, if
any, were sealed.
(i) Functional performance testing.
(1) Written, repeatable test procedures must
be prepared specifically for the project and must be used to functionally test
equipment, components, subsystems, systems, and sequences and modes of
operation. Test procedures must be documented to describe the individual test
procedure, the expected system response, and acceptance criteria for each
procedure.
(2) Testing
documentation must identify the actual system response and must provide any
pertinent observations or discussion.
(3) After initial check-out has been verified
and approved by the commissioning authority, then the following must be tested:
(i) Each sequence in the sequence of
operations must be tested. Additionally, other significant modes, sequences and
control strategies not mentioned in the written sequences must be tested. The
testing must include the following:
(a)
start-up;
(b) shutdown;
(c) unoccupied and manual modes;
(d) modulation up and down the unit's range
of capacity, if applicable;
(e)
staging, if applicable;
(f) power
failure/power down;
(g)
alarms;
(h) backup upon failure;
and
(i) interlocks with other
equipment.
(ii) The functional
performance of each type of component, equipment, subsystem, and system must be
tested using a minimum sample for each type of component, equipment, subsystem
and system. If any component, equipment, subsystem or system in the minimum
sample is found not to operate as required in the construction documents, then
an additional minimum sample of each type found not to be operating as required
must be tested until all units in a minimum sample are found to be operating as
required.
(iii) Equipment must be
tested to demonstrate performance under near-design conditions. To this end,
tests on respective HVAC equipment and systems must be executed during both the
heating and cooling season. However, overriding of control values to simulate
cooling conditions during the heating season, and heating conditions during the
cooling season is allowed where it would not affect the demonstrated
performance required in the construction documents for the component,
equipment, subsystem, system, or mode or sequence of operation being tested.
Where the conditions listed above in this paragraph are not met, seasonally
deferred testing must be undertaken.
(iv) The central plant (heating and cooling)
must have its efficiency recorded for later reference by operations
staff.
(v) Functional performance
testing must be done using manual methods, or control system trend logs and
read-outs, or stand-alone data loggers, as deemed appropriate by the
commissioning authority.
(j) Training.
(1) The commissioning authority must assemble
written verification that training of operations and maintenance personnel was
conducted for all commissioned features and systems.
(2) The training program for operations and
maintenance personnel must include instructional and demonstration
portions.
(3) The owner must
identify for the purpose of training the specific in-house personnel or
contracted organization that will be responsible for the operations and
maintenance for the building. Training must be performed within six months of
the date that either the initial or subsequent statement of commissioning
certification, as appropriate as determined by the commissioning authority, has
been executed. Qualified personnel must perform training for a sufficient
duration of time to ensure that facility staff for the building has all the
information they need to properly operate, maintain and replace each feature or
system that is commissioned.
(4) In
addition, if operations and maintenance personnel change during the period that
the tax credit provided for in this part is taken, the replacement personnel
must receive the training required by these regulations. Written verification
that this training was conducted must be maintained.
(5) The operations and maintenance manual,
and the systems and energy management manual must be available for and used for
the training.
(6) The instructional
portion of the training program must cover at least the following:
(i) general purpose of each building system
(i.e., design intent) including theory of operation, capabilities and
limitations, and modes of control and sequences of operation in the subject
building;
(ii) use of the
operations and maintenance manual and of the systems and energy management
manual;
(iii) review of control
drawings and schematics;
(iv)
procedures for start-up, shutdown, seasonal changeover, normal operation,
unoccupied operation, and manual operation;
(v) controls set-up and
programming;
(vi)
troubleshooting;
(vii)
alarms;
(viii) interactions with
other systems;
(ix) operational
monitoring and record keeping, including what should be monitored, what useful
information can come from monitored data, and why that information is important
to analyzing system operation;
(x)
adjustments and optimizing methods for energy conservation;
(xi) relevant health and safety
issues;
(xii) inspection, service,
and maintenance requirements for each system, including any requirements for
special skills and knowledge that may best be met by specialized service
contractors;
(xiii) sources for
replacement parts/equipment;
(xiv)
tenant interaction issues; and
(xv)
why certain features are environmentally responsive (i.e., save energy, improve
indoor air quality (IAQ), reduce toxic materials, reduce waste).
(7) The demonstration portion of
the training program must include at least the following:
(i) Operation of each system, or typical
examples if there are several similar systems in the building.
(ii) Start-up and shutdown procedures,
operation under all specified modes of control and sequences of operation, and
the correct procedures under emergency or abnormal conditions.
(iii) Procedures necessary for effective
operational monitoring, as appropriate, but particularly for projects with
direct digital control systems incorporating trending and graphing
features.
(k)
Manuals.
(1) Operations and maintenance
(O&M) manual.
(i) The operations and
maintenance data must be complete and must be accessible by the operations and
maintenance personnel and the owner.
(ii) The operations and maintenance manual
must include for each piece of equipment and each system:
(a) the name, address and telephone number of
the manufacturer or vendor and installing contractor;
(b) submittal data; and
(c) operations and maintenance instructions
with the models and features for the subject site clearly marked.
(iii) The operations and
maintenance manual must be edited to include only data for equipment that is
actually installed. The data must include the following:
(a) instructions for installation,
maintenance, replacement, start-up;
(b) special maintenance requirements and
sources for replacement parts/equipment;
(c) parts list;
(d) list of special tools required;
(e) performance data; and
(f) warranty information.
(iv) The manual must also include
an as-built documentation package for controls that includes information
related to the following:
(a) normal
operation;
(b) shutdown;
(c) unoccupied operation;
(d) seasonal changeover;
(e) manual operation;
(f) controls set-up and
programming;
(g)
troubleshooting;
(h)
alarms;
(i) control drawings and
schematics; and
(j) final sequences
of operation.
(2) Systems and energy management manual.
(i) In addition to the operations and
maintenance manual and the commissioning report, a systems and energy
management manual must be developed and delivered to the owner.
(ii) The following components must be
included in the systems and energy management manual even though some parts may
also be found in the operations and maintenance manual:
(a) narratives for the final design intent
and basis of design, including brief descriptions of each system;
(b) final sequences of operations for all
equipment;
(c) procedures for
seasonal start-up and shutdown, manual and restart operation;
(d) as-built control drawings;
(e) for all energy-saving features and
strategies, rationale description, operating instructions, and caveats about
their function and maintenance relative to energy use;
(f) recommendations and brief method for
appropriate accounting of energy use of the whole building.
(g) recommendations for re-calibration
frequency of sensors and actuators by type and use;
(h) plans for continuous commissioning or
recommended frequency for re-commissioning by equipment type, with reference to
tests conducted during initial commissioning;
(i) recommendations regarding seasonal
operational issues affecting energy use;
(j) list of all user-adjustable set points
and reset schedules, with a discussion of the purpose of each and the range of
reasonable adjustments with energy implications;
(k) schedule of how frequently to review the
various setpoints and reset schedules to ensure they still are at current,
relevant, and efficient values;
(l)
list of time-of-day schedules and a frequency to review them for relevance and
efficiency;
(m) guidelines for
establishing and tracking benchmarks for building energy use and primary plant
equipment efficiencies;
(n)
guidelines for ensuring that future renovations and equipment upgrades will not
result in decreased energy efficiency and will maintain the design
intent;
(o) list of diagnostic
tools, with a description of their use, that will assist facility staff for the
building in operating equipment more efficiently; and
(p) a copy of the commissioning report;
and
(q) index of all commissioning
documents with notation as to their location.
(l) Commissioning report.
(1) After all commissioning tasks except
seasonally deferred testing have been completed, a commissioning report must be
delivered to the owner.
(2) The
report must include:
(i) an executive
summary;
(ii) list of participants
and their respective roles;
(iii) a
brief building description;
(iv) an
overview of the scope of commissioning and testing;
(v) a general description of testing and
verification methods; and
(vi) a
list of each feature or system commissioned.
(3) For each piece of commissioned equipment,
the report must contain the determination of the commissioning authority
regarding the adequacy of the equipment, documentation and training.
(4) The commissioning report must address the
following areas:
(i) adequacy of equipment
with respect to construction documents and design intent;
(ii) equipment installation;
(iii) functional performance and
efficiency;
(iv) equipment
documentation;
(v) operations and
maintenance review and recommendations; and
(vi) operator training.
(5) The functional performance and efficiency
section for each piece of equipment must identify the verification method used
(manual testing, trend logs of the building automation system, data loggers)
and must include observations and conclusions from the testing.
(6) The report must also include a list of
outstanding commissioning issues and any testing that is scheduled for a later
date due to weather conditions (i.e., seasonally deferred testing).
(i) All outstanding deficiencies identified
during or as a result of commissioning activities as required by this subpart
must have been corrected or must be separately listed and highlighted in the
commissioning report.
(ii) Each
noncompliance issue must be referenced to where the deficiency is documented
(e.g., the specific functional test, inspection, trend log).
(7) Appendixes must contain
acquired sequence documentation, logs, meeting minutes, progress reports,
deficiency lists, site visit reports, findings, unresolved issues,
communications, and other relevant information. Documentation must be provided
in a separate labeled binder for the following:
(i) start-up and checkout in accordance to
subdivision (h) of this section;
(ii) functional performance testing (along
with blank forms for the operators); and
(iii) as available, data obtained from
monitoring, and analysis of those data.
(8) If components, equipment, subsystems,
systems, controls, or sequences of operations as-built are different than
required in the original construction documents, then the commissioning report
must list these differences. In addition, the commissioning report must state
that the computer models used to calculate energy use to demonstrate compliance
with this Part must be revised to reflect the difference listed between the
as-built conditions and original modeling assumptions and inputs and the listed
deficiencies which have not been corrected. The commissioning report must also
state that the revised energy models must be re-run to demonstrate that the
energy performance is in compliance with the energy use provisions specified in
section
638.7(c)
of this Part.
(9) Once the
seasonally deferred testing has been completed, the commissioning authority
must issue an addendum to the commissioning report, or must re-issue the
commissioning report, using the same criteria and methods as in the initial
commissioning report.