(a) The owner or operator of any process subject to the provisions of this Part for which an application for a permit to construct is received by the commissioner after October 23, 1974, must:
(b) The owner or operator of any process subject to the provisions of this Part for which an application for a permit to construct was received by the commissioner before October 24, 1974, must:
(c) Weighing devices used to comply with the requirements of this section must have an accuracy of +-5.0 percent over their operating range.
(d) Records required by this section must be retained for at least two years following the date on which the measurements were made.