(a) Upon completion of each design phase of the project, the corporation shall notify the municipality and, until the municipality has given the corporation its approval in writing of such phase, the corporation shall not proceed to any subsequent phase unless authorized in writing by the municipality.

(b) Upon receipt of bids for construction, the corporation shall not award any construction contracts until the municipality has given the corporation its approval in writing to award any such contract.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.