New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter XXIX - Susquehanna River Basin Commission
Part 1806 - Review And Approval Of Projects
Standards for Review and Approval
Section 1806.23 - Standards for water withdrawals
Universal Citation: 21 NY Comp Codes Rules and Regs ยง 1806.23
Current through Register Vol. 46, No. 39, September 25, 2024
(a) The project sponsors of all withdrawals subject to review and approval under section 1806.4, 1806.5 or 1806.6 of this Part shall comply with the following standards, in addition to those required pursuant to section 1806.21 of this Part.
(b) Limitations on withdrawals.
(1) The commission may limit withdrawals to
the amount (quantity and rate) of water that is needed to meet the reasonably
foreseeable needs of the project sponsor.
(2) The commission may deny an application,
limit or condition an approval to ensure that the withdrawal will not cause
significant adverse impacts to the water resources of the basin. The commission
may consider, without limitation, the following in its consideration of adverse
impacts: Lowering of groundwater or stream flow levels; rendering competing
supplies unreliable; affecting other water uses; causing water quality
degradation that may be injurious to any existing or potential water use;
affecting fish, wildlife or other living resources or their habitat; causing
permanent loss of aquifer storage capacity; or affecting low flow of perennial
or intermittent streams.
(3) The
commission may impose limitations or conditions to mitigate impacts, including
without limitation:
(i) limit the quantity,
timing or rate of withdrawal or level of drawdown;
(ii) require the project sponsor to provide,
at its own expense, an alternate water supply or other mitigating
measures;
(iii) require the project
sponsor to implement and properly maintain special monitoring
measures;
(iv) require the project
sponsor to implement and properly maintain stream flow protection
measures;
(v) require the project
sponsor to develop and implement an operations plan acceptable to the
commission.
(4) The
commission may require the project sponsor to undertake the following, to
ensure its ability to meet its present or reasonably foreseeable water needs
from available groundwater or surface water without limitation:
(i) investigate additional sources or storage
options to meet the demand of the project;
(ii) submit a water resource development plan
that shall include, without limitation, sufficient data to address any supply
deficiencies, identify alternative water supply options, and support existing
and proposed future withdrawals.
Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.