New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter XXIX - Susquehanna River Basin Commission
Part 1806 - Review And Approval Of Projects
General Provisions
Section 1806.5 - Projects that may require review and approval

Current through Register Vol. 46, No. 12, March 20, 2024

(a) The following projects, if not otherwise requiring review and approval under section 1806.4 of this Part, and provided that the project sponsor is notified in writing by the executive director, may be subject to commission review and approval as determined by the commission or the executive director:

(1) projects that may affect interstate water quality;

(2) projects within a member state that have the potential to affect waters within another member state. This includes, but is not limited to, projects which have the potential to alter the physical, biological, chemical or hydrological characteristics of water resources of interstate streams designated by the commission under separate resolution;

(3) projects that may have a significant effect upon the comprehensive plan;

(4) projects not included in paragraphs (1) through (3) of this subdivision, but which could have an adverse, adverse cumulative, or interstate effect on the water resources of the basin.

(b) Determinations by the executive director may be appealed to the commission within 30 days after receipt of notice of such determination as set forth in section 1808.2 of this Part.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.