New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter XXIX - Susquehanna River Basin Commission
Part 1806 - Review And Approval Of Projects
Application Procedure
Section 1806.18 - Approval modifications
Current through Register Vol. 46, No. 39, September 25, 2024
(a) General.
A project sponsor shall submit an application for modification of a current approval prior to making a change in the design, operational plans, or use as presented in the application upon which the approval was originally issued, and that will affect the terms and conditions of the current approval.
(b) Applications for modification.
A project sponsor may apply for a modification of a current approval by submitting an application for modification to the commission.
(c) Minor modifications.
The following are minor modifications:
(d) Major modifications.
Major modifications are changes not considered to be minor modifications. Major modifications may include, but are not limited to:
(e) Notice and approval.