New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter XXIX - Susquehanna River Basin Commission
Part 1806 - Review And Approval Of Projects
Application Procedure
Section 1806.12 - Constant-rate aquifer testing

Current through Register Vol. 46, No. 12, March 20, 2024

(a) Prior to submission of an application pursuant to section 1806.13 of this Part, a project sponsor seeking approval to withdraw or increase a withdrawal of groundwater shall perform a constant-rate aquifer test in accordance with this section.

(b) The project sponsor shall prepare a constant-rate aquifer test plan for prior review and approval by commission staff before testing is undertaken. Such plan shall include a groundwater availability analysis to determine the availability of water during a 1-in-10-year recurrence interval.

(c) Unless otherwise specified, approval of a test plan is valid for two years from the date of approval.

(d) Approval of a test plan shall not be construed to limit the authority of the commission to require additional testing or monitoring.

(e) The project sponsor may be required, at its expense, to provide temporary water supply if an aquifer test results in interference with an existing water use.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.