New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter X - Power Authority Of The State Of New York
Part 461 - Implementation Of The State Environmental Quality Review Act
Section 461.13 - Decisionmaking and findings requirements

Current through Register Vol. 46, No. 12, March 20, 2024

(a) Prior to the Power Authority's decision on an action which has been the subject of a final EIS, it shall afford agencies and the public a reasonable time period (not less than 10 calendar days) in which to consider the final EIS.

(b) The Power Authority, by its trustees or their delegate, shall not make a final decision to commence, engage in, fund or approve action that has been the subject of a final Federal or a final SEQRA EIS until it has:

(1) given consideration to the final EIS;

(2) made a written finding that the requirements of this Part have been met and the action is:
(i) consistent with social, economic and other essential considerations among the reasonable alternatives thereto, the action to be carried out or approved is one which minimizes or avoids adverse environmental effects to the maximum extent practicable, including the effects disclosed in the relevant environmental impact statement; and

(ii) consistent with social, economic and other essential considerations, to the maximum extent practicable, adverse environmental effects revealed in the environmental impact statement process will be minimized or avoided by incorporating as conditions to the decision those mitigative measures which were identified as practicable; and

(3) prepared a written statement of the facts and conclusions relied upon in the EIS, supporting its decision and indicating the social, economic and other factors and standards which formed the basis of its decision.

(4) When the action is in the coastal area within the boundaries of an approved local waterfront revitalization program, and the action is one identified by the Secretary of State pursuant to section 916(1)(a) of the Executive Law, the action must be consistent, to the maximum extent practicable, with the applicable policies of such program.

(c) The Power Authority shall not make a decision to disapprove an action based upon the EIS until it has prepared a written statement of the facts and conclusions relied on in the EIS or comments provided thereon.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.