New York Codes, Rules and Regulations
Title 21 - Miscellaneous
Chapter LXXIV - New York City School Construction Authority
Part 9600 - Guidelines For Qualification And Evaluation Of Contractors, Subcontractors, Consultants, Vendors And Suppliers For Contracts On All Phases Of Construction, Reconstruction, Improvement Or Rehabilitation Of New York City Schools
Section 9600.5 - Procedure for disqualification and revocation

Current through Register Vol. 46, No. 12, March 20, 2024

(a) In the event the authority concludes that there may be sufficient evidence to warrant denial/revocation of a firm's prequalification, the authority shall notify the contractor of its proposed denial or revocation of prequalification status, the reasons for this denial/revocation, and the period of disqualification.

(b) A contractor so notified may request a meeting, at which the contractor shall have the opportunity to present evidence that might result in reconsideration of the authority's preliminary conclusion to deny or revoke the contractor's prequalification.

(c) The authority shall provide to the contractor final written notification of its determination.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.