New York Codes, Rules and Regulations
Title 17 - DEPARTMENT OF TRANSPORTATION
Chapter IV - Highways
Subchapter A - Property Acquisition
Part 100 - Interest On Payments Pursuant To Agreements Of Adjustment Or Agreements For Partial Payment Of Claims Arising Out Of The Appropriation Of Property
Section 100.1 - Negotiated settlements
Current through Register Vol. 46, No. 39, September 25, 2024
Interest at the rate of four percent per annum to August 1, 1966 and at the rate of six percent per annum thereafter will be paid by the State on either agreements of adjustment or agreements for partial and advance payment approved on and after July 1, 1962 by the Commissioner of Transportation and, when required by statute, by the Comptroller regardless of when the property was acquired by the State on the following conditions:
(a) Interest shall accrue on all such claims:
(b) Suspensions. Such interest will be paid on agreements of adjustment and agreements for partial and advance payment from such dates, whichever is earlier, to the date of payment of the claim except as follows:
(c) Extensions. In those cases where the Commissioner of Transportation is restrained by judicial order or proceedings, or delayed by other causes, from proceeding with the adjustment of claims, the said period of six months referred to in the subdivisions above may be extended by the commissioner for the duration of such restraint or delay and for such additional period up to and not to exceed six months after the restraint or delay is terminated.