(a) Each operator of a buried pipeline shall carry out a written program to prevent damage to that pipeline by excavation activities in accordance with 16 NYCRR Part 753, Protection of Underground Facilities. Each operator of a buried pipeline, except for gathering lines in Class 1 and 2 locations, must participate in the one-call notification system that covers the areas of the State in which those pipeline facilities are located.

(b) Where the operator has reason to believe damage could be done by the excavation activities, the pipeline must be inspected as frequently as necessary during and after the activities to verify the integrity of the pipeline.

(c) In the case of blasting, each inspection must include a leakage survey.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.