(a) No person may operate a segment of pipeline unless it is operated in accordance with this Part.

(b) Each operator shall prepare and file a detailed written operating and maintenance plan for complying with all the provisions of this Part before operations of a pipeline system commence; it must be reviewed and updated by the operator at intervals not exceeding 15 months, but at least once each calendar year. Appropriate parts of the plan must be kept at locations where operations and maintenance procedures are conducted. Revisions to these written procedures shall be submitted at least 30 days prior to the effective date. Minor revisions that do not affect the intent of the procedure may be implemented immediately and submitted on a quarterly basis.

(c) Each operator shall establish and maintain the maps of its transmission lines and distribution mains and maps or records of its service lines as necessary to administer its operating and maintenance plan.

(d) Each operator shall satisfactorily conform with the program submitted.

(e) The commission may require an operator to amend its operating and maintenance plan as necessary to provide a reasonable level of safety.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.