New York Codes, Rules and Regulations
Title 16 - DEPARTMENT OF PUBLIC SERVICE
Chapter I - RULES OF PROCEDURE
Subchapter G - Certificates Of Environmental Compatibility And Public Need
Part 85 - General Procedures
Subpart 85-2 - Procedures with Respect to All Electric Transmission Lines and Fuel Gas Transmission Lines 10 or More Miles Long
Section 85-2.15 - Dismissal of an application

Current through Register Vol. 47, No. 12, March 26, 2025

Whenever it shall appear that the statutory requirements for a certificate cannot be met, the commission may dismiss the application and terminate the proceedings upon the motion of any party or staff counsel, or upon its own motion.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.