Section 14-9.21 - Inspector's test gage connection
Universal Citation: 12 NY Comp Codes Rules and Regs § 14-9.21
Current through Register Vol. 47, No. 12, March 26, 2025
Each boiler shall be provided with a one-quarter inch pipe size valved connection for the exclusive purpose of attaching a test gage when the boiler is in service, so that the accuracy of the boiler steam gage can be ascertained.
Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.