No high pressure boiler shall be operated until an internal and external inspection has been made by the commissioner or an insurance company. There shall be regular inspections of every boiler subject to the provisions of this Part made at intervals no less frequent than the following:

Internal External
Low Pressure Steam Boilers 3 years 2 years
Low Pressure Hot Water Boilers 5 years 2 years
High Pressure Steam Boilers 1 year 1 year2
High Pressure Hot Water Boilers 3 years1 1 year2

Footnotes

1 If equipped with manholes and handholes, an annual internal inspection is required.

2 Approximately 6 months after each internal inspection.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.