New York Codes, Rules and Regulations
Title 12 - DEPARTMENT OF LABOR
Chapter I - Industrial Board Of Appeals
Subchapter A - The Industrial Code
Part 14 - Construction, Installation, Inspection And Maintenance Of High Pressure Boilers; Construction Of Unfired Pressure Vessels
Subpart 14-1 - Definitions
Section 14-1.2 - Inspection frequency
Universal Citation: 12 NY Comp Codes Rules and Regs ยง 14-1.2
Current through Register Vol. 46, No. 12, March 20, 2024
No high pressure boiler shall be operated until an internal and external inspection has been made by the commissioner or an insurance company. There shall be regular inspections of every boiler subject to the provisions of this Part made at intervals no less frequent than the following:
Internal | External | |
Low Pressure Steam Boilers | 3 years | 2 years |
Low Pressure Hot Water Boilers | 5 years | 2 years |
High Pressure Steam Boilers | 1 year | 1 year2 |
High Pressure Hot Water Boilers | 3 years1 | 1 year2 |
Footnotes
1 If equipped with manholes and handholes, an annual internal inspection is required.
2 Approximately 6 months after each internal inspection.
Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.