New York Codes, Rules and Regulations
Title 10 - DEPARTMENT OF HEALTH
Chapter I - State Sanitary Code
Part 7 - TEMPORARY RESIDENCES, MASS GATHERINGS AND CHILDREN'S CAMPS
Subpart 7-1 - Temporary Residences (hotels, Motels And Cabin Colonies)
Operation, Supervision and Maintenance
Section 7-1.10 - Sewage collection and treatment

Current through Register Vol. 46, No. 39, September 25, 2024

(a) Facilities shall be provided and maintained for the satisfactory treatment and disposal of sewage. In addition, such facilities shall meet the following requirements:

(1) Submission of plans. A plan for new or modified sewage treatment facilities shall be submitted to the permit-issuing official at least 60 days prior to beginning construction.

(2) Plan approval and construction. Plans for sewage treatment system construction or improvements shall be approved prior to construction by the permit-issuing official and/or New York State Department of Environmental Conservation. No construction of new or modified sewage treatment facilities shall commence until all required approvals have been obtained. Construction shall be in accordance with the approved plans.

(b) The presence of inadequately treated sewage on the surface of the ground is prohibited.

Disclaimer: These regulations may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.