New Mexico Administrative Code
Title 20 - ENVIRONMENTAL PROTECTION
Chapter 7 - WASTEWATER AND WATER SUPPLY FACILITIES
Part 9 - COLONIAS WASTE WATER GRANT POLICIES
Section 20.7.9.400 - PAYMENT REQUIREMENTS
Universal Citation: 20 NM Admin Code 20.7.9.400
Current through Register Vol. 35, No. 18, September 24, 2024
A. Interim Payments:
(1) For satisfactory
performance of all work and services required to be performed under the terms
of the grant agreement, NMED shall reimburse the Grantee its actual costs
incurred. The Grantee may submit requests for reimbursement as often as every
month. NMED shall disburse funds to the Grantee when NMED determines, in its
sole discretion, that expenditures have been properly documented, as provided
for in the general requirements for allowable and unallowable costs, accounting
procedures, and record keeping. Copies of all pay request vouchers shall be
submitted to the NMED with request for payment. Two copies of all requests
shall be submitted on the appropriate form furnished by NMED and shall be
accompanied by appropriate documentation to assure that those costs are correct
and within the approved scope of work and attached budget form. Requests shall
include expenditures to date by category.
(2) Unless good cause exists which would
justify a higher amount, the NMED shall withhold five percent of payments due
and owing a contractor from the Grantee until fifty percent of the contract has
been billed. Unless good cause exists, the NMED shall not withhold any
additional retainage from billings after fifty percent of the contract has been
billed by the Grantee and approved by the NMED.
(3) Such retainage shall be held by NMED
pending its final project inspection and acceptance, which shall be performed
promptly and the results of which convey to the Grantee in writing. The project
will not be considered complete until the work as defined in the grant
agreement and the State approved plans and specifications has been fully
performed and finally and unconditionally accepted by the Grantee and
NMED.
(4) Interim payments will be
made as the work progresses. Said payments will be based upon requests for
payment prepared and certified by the Grantee or the Grantee's engineer to
include value of work performed, materials on hand, and materials in place in
accordance with the contract. Interim payments for engineering, inspection,
legal services, or other approved services shall be made in accordance with the
approved contracts or agreements.
(5) Any portion of funds paid by NMED to the
Grantee which remain unexpended after completion of the project shall revert to
Colonias Wastewater Construction Grant Program.
(6) The Grantee shall furnish the NMED with
an estimated disbursement schedule at the beginning of the project.
B. Final Payment: Upon completion of the project, final payment shall be made after final inspection has been conducted and the following have been provided, reviewed, and approved by the NMED:
(1) The Grantee's certified request for
payment prepared by the engineer and approved by the NMED.
(2) A statement by the project engineer that
work has been satisfactorily completed and the contractor has fulfilled all of
the obligations required under the contract documents with the Grantee, or if
payment and materials performance bonds are "called," an acceptable close-out
settlement to the Grantee and contractors shall be submitted to the NMED for
review and approval.
(3) Final
engineering statement and recap of all engineering services, legal,
administrative, and other eligible and ineligible expenses and final request
for disbursement.
(4) Certification
by the Grantee that the labor standards contract provisions have been
met.
(5) Final project inspection
report prepared by the engineer.
(6) Record drawings and, if applicable, an
operation and maintenance manual.
(7) Final budget showing all funding sources
utilized for costs incurred for the project by designated budget
categories.
(8) Written consent of
the surety, if any, to final payment is prepared and submitted.
(9) For projects which receive planning
grants but do not proceed to the design/construction phase, completion of the
project is defined as substantial completion of the project description in the
Grant agreement as determined by the NMED.
(10) The final payment to the consultant will
be made after the one year performance period has ended and the granted has
provided project performance certification.
Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.