A. Purpose. Under certain circumstances, the building of a component/portion of a wastewater treatment system may be justified in advance of completing all environmental review requirements for the remainder of the system(s). When there are overriding considerations of cost or impaired program effectiveness the responsible official may approve a loan for a discrete component of a complete wastewater treatment system(s). The process of partitioning the environmental review for the discrete component shall comply with the criteria and procedures described in subsection (B) of this section. In addition, all reasonable alternatives for the overall wastewater treatment works system(s), of which the component is a part, shall have been previously identified and each part of the environmental review for the remainder of the overall facilities plan shall comply with all requirements under Sections 14 and 15 of 20.7.7 NMAC.
B. Criteria for partitioning. The project component must:
C. Request for partitioning. The applicant's request for partitioning must contain the following:
D. Approval of requests for partitioning. The responsible official shall: