Current through Register Vol. 35, No. 6, March 26, 2024
A. Owners and operators shall implement the final remediation plan after department approval in accordance with a timeline approved by the department or the timeline set forth in Subsection E of 20.5.119.1900 NMAC. Owners and operators shall employ a professional engineer to ensure conformance with the final remediation plan including excavation and installation, commissioning and operation of the system.
B. When the remediation plan includes mechanical or electrical equipment, engineered fill, pinning, shoring or slope stability analysis:
C. Owners and operators shall obtain written approval from the department prior to implementing any change to the department-approved engineering design.
D. Following implementation of the final remediation plan, owners and operators shall submit an "as-built" report signed and sealed by the project professional engineer including: