New Mexico Administrative Code
Title 20 - ENVIRONMENTAL PROTECTION
Chapter 2 - AIR QUALITY (STATEWIDE)
Part 99 - CONFORMITY TO THE STATE IMPLEMENTATION PLAN OF TRANSPORTATION PLANS, PROGRAMS, AND PROJECTS
Section 20.2.99.134 - CRITERIA AND PROCEDURES - PROJECTS FROM A TRANSPORTATION PLAN AND TIP
Current through Register Vol. 35, No. 18, September 24, 2024
A. The project must come from a conforming transportation plan and TIP. If this criterion is not satisfied, the project must satisfy all criteria in table 1 of Subsection B of 20.2.99.128 NMAC for a project not from a conforming transportation plan and TIP. A project is considered to be from a conforming transportation plan if it meets the requirements of Subsection B of 20.2.99.134 NMAC and from a conforming TIP if it meets the requirements of Subsection C of 20.2.99.134 NMAC. Special provisions for TCMs in an applicable implementation plan are provided in Subsection D of 20.2.99.134 NMAC.
B. A project is considered to be from a conforming transportation plan if one of the following conditions apply:
C. A project is considered to be from a conforming TIP if the following conditions are met:
D. TCMs: This criterion is not required to be satisfied for TCMs specifically included in an applicable implementation plan.
E. Notwithstanding the requirements of Subsections A, B, and C of this section (20.2.99.134 NMAC), a project must meet the requirements of Subsection B of 20.2.99.111 NMAC during the twelve (12) month lapse grace period.