New Mexico Administrative Code
Title 19 - NATURAL RESOURCES AND WILDLIFE
Chapter 8 - COAL MINING
Part 7 - PERMIT APPLICATIONS - MINIMUM REQUIREMENTS FOR LEGAL, FINANCIAL, COMPLIANCE AND RELATED INFORMATION
Section 19.8.7.705 - PERMIT TERM INFORMATION
Universal Citation: 19 NM Admin Code 19.8.7.705
Current through Register Vol. 35, No. 24, December 23, 2024
A. Timing and extent of operations.
(1) Each
application shall state the anticipated or actual starting and termination date
of each phase of the surface coal mining operations and the anticipated number
of acres of surface land to be affected for each phase of mining and over the
total life of the permit.
(2) The
horizontal and vertical extent of the proposed workings for each phase of the
operation for the life of the permit shall be shown for underground
mining.
B. If the applicant proposes to conduct the surface coal mining operations in excess of 5 years, the application shall contain the information needed for the showing required under Subsection A of 19.8.11.1111 NMAC.
Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.