A. Diversions from perennial and intermittent streams within the permit area shall be approved by the director, if he finds that the diversions comply with:
B. When streamflow is allowed to be diverted, the stream channel diversion shall be designed, constructed, and removed in accordance with the following:
C. The design and construction of all stream channel diversions of perennial and intermittent streams shall be certified by a qualified registered professional engineer as meeting the performance standards of 19.8.20 NMAC and any design criteria set by the director.
D. When no longer needed to achieve the purpose for which they were authorized, all temporary stream channel diversions shall be removed and the affected land regraded and revegetated, in accordance with 19.8.20.2007, 2008, 2054 through 2058, and 2060 through 2066 NMAC. At the time diversions were removed, downstream water treatment facilities previously protected by the diversion shall be modified or removed to prevent overtopping or failure of the facilities. The requirement shall not relieve the person who conducts the surface coal mining operations from maintenance of a water treatment facility otherwise required under 19.8.20 NMAC or the permit.
E. When permanent diversions are constructed or stream channels restored, after temporary diversions, the operator shall: