Prior to the state engineer approving an application for Underground Storage and Recovery, the applicant must meet its burden of proof. The applicant has the burden of proving:
A. the applicant has the technical and financial capability to construct and operate the project;
B. the project is hydrologically feasible;
C. the project will not impair existing water rights or the state's interstate obligations;
D. the project will not be contrary to the conservation of water within the state;
E. the project will not be detrimental to the public welfare of the state;
F. the applicant has a valid water right for the recharge water quantified by one of the following legal processes:
G. the applicant will obtain all other permits for the project required by state and federal law. A project shall not be operated under the Act until an applicant has obtained all other state and federal permits required for the project; and
H. the project will not impair water rights or cause harm to owners or land within the area of hydrologic effect.