A permittee shall notify the division with:
A. a written notice of intent to engage in any one of the following activities:
(1) make
a minor change in the operation of the well (minor changes include changing
capillary tubing, pulling or replacing a pump or any other change the division
considers a minor change);
(2)
conduct a spinner, pressure or temperature survey test or another test that
does not modify the well structure;
(3) conduct a flow test on a production
well;
(4) perform routine
maintenance on a well;
(5) removal
of fluids from on-site pits or closed-loop systems per Paragraph (3) of
Subsection D of
19.11.4.17 NMAC; or
(6) change in location of a well that is
within the approved area of a geothermal well or facility permit (this will
require the permittee to apply for a minor permit modification pursuant to
Subparagraph F of
19.11.2.10 NMAC so that the permit
will reflect the new location).
B. a written notice of intent and request for approval for any one of the following activities:
(1) activities not specifically approved or
exempted under an existing permit;
(2) activities that do not require a permit
application per
19.11.2.10 NMAC;
(3) tracer tests;
(4) mechanical integrity tests;
(5) increasing depth of a well;
(6) conduct a flow test on an injection
well;
(7) entering or opening a
plugged well;
(8) shooting,
acidizing or fracturing a well;
(9)
abandoning and plugging a well;
(10) directional drilling (drilling in a
direction not intended to be vertical);
(11) changing the construction of a hole or
well, except for injection wells, including placing a plug in the hole or well
and recovering or altering the casing;
(12) conducting a major workover or cleaning
of a well; or
(13) any other
activity for which the division conducts a field inspection or evaluates
information or documentation regarding the construction of a hole or
well.
C. The director may determine, based on the notices submitted under Subsections A or B of 19.11.4.9 NMAC, that the permittee is required to apply for a permit modification in accordance with 19.11.2.10 NMAC.
Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.