New Mexico Administrative Code
Title 19 - NATURAL RESOURCES AND WILDLIFE
Chapter 10 - NON-COAL MINING
Part 6 - NEW MINING OPERATIONS
Section 19.10.6.608 - PERMIT MODIFICATIONS OR REVISION
Current through Register Vol. 35, No. 18, September 24, 2024
A. A permit modification or revision for a mining operation is required for each new discrete processing, leaching, excavation, storage or stockpile unit located within the permit area and not identified in the permit and for each expansion of such a unit identified in the permit that exceeds the design limits specified in the permit.
B. A permit modification or revision shall be required for any change in the approved reclamation plan.
C. An application for a permit modification or revision shall be in a format acceptable to the Director. A permit modification or revision will not be granted unless the Director determines that the proposed modification or revision meets the requirements of 19.10.6 NMAC.
D. Revisions are modifications that require public notice and an opportunity for public hearing pursuant to 19.10.9 NMAC. The Director shall review each request for a permit modification to determine whether it must be processed as a revision.
E. The following actions do not require permit modifications: