Current through Register Vol. 35, No. 18, September 24, 2024
The permit area will be reclaimed to achieve a
self-sustaining ecosystem appropriate for the life zone of the surrounding
areas following closure unless conflicting with the approved post-mining land
use. Each reclamation plan must be developed to meet the site-specific
characteristics of the mining operation and the site.
A. Most Appropriate Technology and Best
Management Practices The mining operation and the reclamation plan shall be
designed and operated using the most appropriate technology and the best
management practices.
B.
Contemporaneous Reclamation Contemporaneous reclamation is required to the
maximum extent practicable and in a manner that is consistent with the approved
reclamation plan.
C. Assure
Protection The mining operation and completed reclamation shall meet the
following requirements established to assure protection of human health and
safety, the environment, wildlife and domestic animals.
(1) Signs, Markers and Safeguarding Measures
will be taken to safeguard the public from unauthorized entry into shafts,
adits, and tunnels and to prevent falls from highwalls or pit edges. Depending
on site-specific characteristics, the following measures shall be required:
(a) closing shafts, adits or tunnels to
prevent entry;
(b) posting warning
signs in locations near hazardous areas;
(c) restricting access to hazardous
areas;
(d) marking the permit area
boundaries;
(e) posting a sign at
the main entrances giving a telephone number of a person to call in the event
of emergencies related to the mine; or
(f) other measures as needed to protect human
safety.
(2) Wildlife
Protection Measures shall be taken to minimize adverse impacts on wildlife and
important habitat. Based on site-specific characteristics, the following
measures will be required:
(a) restricting
access of wildlife and domestic animals to toxic chemicals or otherwise harmful
materials;
(b) minimizing harm to
wildlife habitat during mining; and
(c) reclaiming areas of wildlife habitat if
not in conflict with the approved post-mining land use.
(3) Cultural Resources Cultural resources
listed on or eligible for listing on the National Register of Historic Places
or the State Register of Cultural Properties, and any cemeteries or burial
grounds shall be protected until clearance has been granted by the State
Historic Preservation Office or other appropriate authority.
(4) Hydrologic Balance Operations shall be
planned and conducted to minimize change to the hydrologic balance in both the
permit and potentially affected areas. If not in conflict with the approved
post-mining land use, reclamation shall result in a hydrologic balance similar
to pre-mining conditions unless non-mining impacts have substantially changed
the hydrologic balance.
(a) Operations shall
be designed so that non-point source surface releases of acid or other toxic
substances shall be contained within the permit area, and that all other
surface flows from the disturbed area are treated to meet all applicable state
and federal regulations.
(b) The
disturbed areas shall not contribute suspended solids above background levels,
or where applicable the Water Quality Control Commission's standards, to
intermittent and perennial streams.
(c) To provide data to determine background
levels for surface water entering the permit area, appropriate monitoring shall
be conducted on drainages leading into the permit area.
(d) All diversions of overland flow shall be
designed, constructed and maintained to minimize adverse impacts to the
hydrologic balance and to assure the safety of the public.
(i) No diversion shall be located so as to
increase the potential for landslides.
(ii) Unless site-specific characteristics
require a different standard which is included in the approved permit,
diversions which have watersheds larger than 10 acres shall be designed,
constructed and maintained to safely pass the peak runoff from a 10-year,
24-hour precipitation event.
(iii)
All diversion designs which have watersheds larger than 10 acres shall be
certified by a professional engineer registered in New Mexico as having been
designed in accordance with 19.10 NMAC. Diversion designs shall be kept on-site
or otherwise be made available, upon request, to the Director for
inspection.
(iv) When no longer
needed, temporary diversions shall be removed and the disturbed area
reclaimed.
(5)
Stream Diversions When streams are to be diverted, the stream channel diversion
shall be designed, constructed, and removed in accordance with the following:
(a) unless site-specific characteristics
require different measures to meet the performance standard and are included in
the approved permit, the combination of channel, bank and flood plain
configurations shall be adequate to safely pass the peak run-off of a 10-year,
24-hour precipitation event for temporary diversions, a 100-year, 24-hour
precipitation event for permanent diversions;
(b) the design and construction of all
intermittent and perennial stream channel diversions shall be certified as
meeting 19.10 NMAC by a professional engineer registered in New Mexico.
As-built drawings shall be completed promptly after construction and be
retained on site or otherwise made available upon request to the Director;
and
(c) when no longer needed,
temporary stream channel diversions shall be removed and the disturbed area
reclaimed.
(6)
Impoundments If impoundments are required they shall be designed, constructed
and maintained to minimize adverse impacts to the hydrologic balance and
adjoining property and to assure the safety of the public.
(a) Unless site-specific characteristics
require different measures to meet the performance standard and are included in
the approved permit, impoundments having earthen embankments but not subject to
the jurisdiction of the Mine Safety and Health Administration or the State
Engineer shall:
(i) have a minimum elevation
at the top of the settled embankment of 1.0 foot above the water surface in the
pond with the spillway flowing at the design depth;
(ii) have a top width of the embankment not
less than 6 feet;
(iii) have
combined upstream and downstream side slopes of the settled embankment not less
than 5 horizontal : 1 vertical with neither slope steeper than 2 horizontal : 1
vertical. Slopes shall be vegetated or otherwise stabilized to control
erosion;
(iv) have the embankment
foundation cleared of all vegetative matter, all surfaces sloped to no steeper
than 1 horizontal : 1 vertical and the entire foundation area
scarified;
(v) have fill material
free of vegetative matter and frozen soil;
(vi) have spillways provided to safely
discharge the peak runoff of a 25-year, 24-hour precipitation event, or an
event with a 90-percent chance of not being exceeded for the design life of the
structure; or
(vii) have other
site-specific design criteria for embankments as long as they result in a
minimum static safety factor of 1.3 with water impounded to the design
level;
(viii) be designed and
certified by a professional engineer registered in New Mexico as having been
designed and constructed in accordance with 19.10 NMAC. As-built drawings shall
be completed promptly after construction and be retained on site or otherwise
made available upon request to the Director; and
(ix) if necessary for sediment control be, in
place before any other disturbance to the watershed for the
impoundment.
(b) When no
longer required, impoundments shall be graded to achieve positive drainage
unless:
(i) the surface estate owner has
requested in writing that they be retained;
(ii) they are consistent with the approved
reclamation plan; and
(iii) they
are appropriate for the post-mining land use or the self-sustaining
ecosystem.
(7)
Minimization of Mass Movement All man-made piles such as waste dumps, topsoil
stockpiles and ore piles shall be constructed and maintained to minimize mass
movement.
(8) Riparian and Wetland
Areas Disturbance to riparian and wetland areas shall be minimized during
mining. Adverse effects to riparian and wetland areas shall be mitigated during
reclamation unless the mitigation conflicts with the approved post-mining land
use.
(9) Roads Roads shall be
constructed and maintained to control erosion.
(a) Drainage control structures shall be used
as necessary to control runoff and to minimize erosion, sedimentation and
flooding. Drainage facilities shall be installed as road construction
progresses and shall be capable of safely passing a 10-year, 24 hour
precipitation event unless site-specific characteristics indicate a different
standard is appropriate and is included in the approved permit. Culverts and
drainage pipes shall be constructed and maintained to avoid plugging,
collapsing, or erosion.
(b) Roads
to be constructed in or across intermittent or perennial streams require
site-specific designs to be submitted with the permit application.
(c) Roads to be made permanent must be
approved by the surface owner and be consistent with the approved post-mining
land use.
(10)
Subsidence Control Underground and in situ solution mining activities shall be
planned and conducted, to the extent technologically and economically feasible,
to prevent subsidence which may cause material damage to structures or property
not owned by the operator.
(a) Underground
and in situ solution mining activities near any aquifer that serves as a
significant source of water supply to a public water system shall be conducted
so as to avoid disruption of the aquifer and consequent exchange of ground
water between the aquifer and other strata.
(b) Underground and in situ solution mining
activities conducted beneath or adjacent to any perennial stream must be
performed in a manner so that subsidence is not likely to cause material damage
to streams, water bodies and associated structures.
(11) Explosives Blasting shall be conducted
to prevent injury to persons or damage to property not owned by the operator.
Fly rock shall be confined to the permit area. The Director may require a
detailed blasting plan, pre-blast surveys or specify blast design limits to
control possible adverse effects to structures.
D. Site Stabilization & Configuration The
permit area shall be stabilized, to the extent practicable, to minimize future
impact to the environment and protect air and water resources. The final
surface configuration of the disturbed area shall be suitable for achieving a
self-sustaining ecosystem or approved post-mining land use.
(1) Final slopes and drainage configurations
must be compatible with a self-sustaining ecosystem or approved post-mining
land use.
(2) Backfilling or
partial backfilling shall be required only when necessary to achieve
reclamation objectives that cannot be accomplished through other mitigation
measures.
(3) All reconstructed
slopes, embankments and roads shall be designed, constructed and maintained to
minimize mass movement.
(4)
Measures must be taken to reduce, to the extent practicable, the formation of
acid and other toxic drainage that may otherwise occur following closure to
prevent releases that cause federal or state standards to be
exceeded.
(5) Nonpoint source
surface releases for acid or other toxic substances shall be contained within
the permit area.
E.
Topsoil Where sufficient topsoil is present, the operator shall take measures
to preserve it from erosion or contamination and assure that it is in a usable
condition for sustaining vegetation when needed. The following requirements
shall be met unless site-specific characteristics mandate different
requirements and those requirements are included in the approved permit.
(1) Topsoil and topdressing shall be sampled
and analyzed for vegetation establishment suitability:
(a) sample spacing and interval shall be
based on site-specific materials; and
(b) suitability will be identified by
analysis based on site-specific materials.
(2) If revegetation is a component of the
reclamation plan and if sufficient topsoil is present in the disturbed or
borrow areas, it shall be collected and preserved to the extent practicable.
Sufficient topsoil means that it is of sufficient quality to conform to the
definition of topsoil. Any necessary topdressing may be obtained from areas to
be disturbed or borrow areas and shall be salvaged separately from other
materials as needed to ensure its availability for distribution when needed for
reclamation.
(3) Where direct
distribution of topsoil or topdressing is not possible, it shall be stockpiled
separately and in a manner to prevent loss of the resource.
(4) Topsoil and topdressing shall be
distributed in a manner to establish and maintain vegetation, consistent with
the approved permit.
(5) After
distribution, topsoiled and topdressed areas shall be stabilized to protect
loss of the resource.
(6) Where
topsoil has been stockpiled for more than one year, the permittee may be
required to conduct analyses to determine if amendments are
necessary.
F. Erosion
Control Reclamation of disturbed lands must result in a condition that controls
erosion. Revegetated lands must not contribute suspended solids above
background levels, or where applicable the Water Quality Control Commission's
standards, to streamflow of intermittent and perennial streams. Acceptable
practices to control erosion include but are not limited to the following:
(1) stabilizing disturbed areas through land
shaping, berming, or grading to final contour;
(2) minimizing reconstructed slope lengths
and gradients;
(3) diverting
runoff;
(4) establishing
vegetation;
(5) regulating channel
velocity of water;
(6) lining
drainage channels with rock, vegetation or other geotechnical materials;
and
(7) mulching.
G. Revegetation To obtain the
release of financial assurance revegetated lands must meet the following
standards:
(1) Revegetation success for a
self-sustaining ecosystem shall be determined through comparison of ground
cover, productivity and diversity and shall be made on the basis of the
following approved reference areas; through the use of technical guidance
procedures published by the U. S. Department of Agriculture; other reasonably
attainable standards approved by the Director; or a combination. Data
collection shall be performed using the same methods and techniques on
reference areas and reclaimed areas.
(a)
foliage or basal cover and productivity of living perennial plants of the
revegetated area shall be established equal to 90 percent of the reference area
or equal to the approved revegetation standard to within a 90-percent
statistical confidence;
(b)
diversity of plant life forms (woody plants, grasses, forbs) shall consider
what is reasonable based on the physical environment of the reclaimed area;
and
(c) woody plant species shall
be established to the approved density with an 80 percent statistical
confidence.
(2) For
areas for which the approved post-mining land use is for wildlife habitat or
forest land, success of vegetation shall be determined on the basis of tree or
shrub stocking (density) and ground cover.
(a) The ground cover of living perennial
plants shall be equal to 90 percent of the native ground cover of the reference
area or the approved standard to within a 90 percent statistical confidence and
shall be adequate to control erosion.
(b) Tree stocking for forest land shall have
stocking rates of plant species equal to 90 percent of the approved reference
area or other approved standard with an 80 percent statistical confidence and
shall be adequate to control erosion.
(c) If wildlife habitat is to be the
post-mining land use, the operator shall select and use plant species on
reclaimed areas based on the following criteria:
(i) their proven nutritional value for fish
and wildlife;
(ii) their uses as
cover and security for wildlife;
(iii) their ability to support and enhance
fish and wildlife habitat; and
(iv)
distribute plant life forms to maximize benefits of edge effect, cover and
other benefits for fish and wildlife.
(3) Revegetation for other post-mining land
shall be consistent with the approved post-mining land use. Site-specific
standards may include standards for foliar or basal cover, production and
diversity and will be included in the approved permit.
H. The operation will be designed to meet
without perpetual care all applicable environmental requirements of the Act,
19.10 NMAC and other laws following closure.