New Mexico Administrative Code
Title 19 - NATURAL RESOURCES AND WILDLIFE
Chapter 10 - NON-COAL MINING
Part 5 - EXISTING MINING OPERATIONS
Section 19.10.5.503 - PERMIT APPROVAL REQUIREMENTS
Current through Register Vol. 35, No. 18, September 24, 2024
A. Unless a proposed closeout plan is submitted with the permit application, the following procedure shall be followed. If a closeout plan is submitted with the permit application, the requirements of 19.10.5.506 NMAC shall also be met.
B. As soon as practicable after receipt of a permit application, the Director shall notify the applicant in writing whether the application is complete. If the application is not complete, the notice shall specify the items missing from the application.
C. The Director shall deliver copies of the complete application or appropriate sections (except those parts of the application designated confidential under Subsection B of 19.10.5.502, provided, however, that the Director shall include with the application a list of the parts withheld and will provide such parts at an agency's specific request) to the Environment Department, the Office of the State Engineer, Department of Game and Fish, the State Forestry Division, the State Historic Preservation Office, and the state or federal land management agency, if applicable, for their information.
D. Within 30 days of receipt of a notice from the Director that the application is complete, the applicant shall, in a form approved by the Director, give public notice of the application pursuant to 19.10.9 NMAC.
E. An application for a permit under 19.10.5 NMAC shall be approved or denied within six months after the application has been determined to be complete.
F. The Director shall approve the application and issue the permit if he finds that: