New Mexico Administrative Code
Title 19 - NATURAL RESOURCES AND WILDLIFE
Chapter 10 - NON-COAL MINING
Part 2 - FEES
Section 19.10.2.202 - ANNUAL FEES
Universal Citation: 19 NM Admin Code 19.10.2.202
Current through Register Vol. 35, No. 18, September 24, 2024
A. The annual fee for an existing mining operation shall be determined by adding:
(1) $800.00 base fee;
(2) $15.00 per acre for the first 50 acres of
currently disturbed surface land plus $3.00 per acre for all disturbed land
over 50 acres;
(3) a fee determined
in accordance with 19.10.2.203 NMAC;
(4) a surcharge of 75% shall be added to the
total annual fees for mining operations that have 500 acres or more disturbed
area in their permit as defined in Paragraph (2) of Subsection D of 19.10.1.7
NMAC; substantially reclaimed acreage as defined in Paragraph (1) of Subsection
F of 19.10.2.202 NMAC will not be counted as disturbed acreage for purposes of
this paragraph;
(5) a surcharge of
50% shall be added to the total annual fees for existing mining operations that
did not obtain an extension in accordance with Subsection D of 19.10.5.501 NMAC
and have not obtained closeout plan approval; and
(6) the annual fee shall be calculated each
year based on cumulative acreage disturbed as of December 31st of the prior
year, and shall be due on or before April 30th of each year until all Mining
Act requirements are met.
B. The annual fee for the new mining operation shall be determined by adding:
(1)
$1,000.00 base fee;
(2) $30.00 per
acre for the first 50 acres of currently disturbed surface land plus $10.00 per
acre for all disturbed land over 50 acres;
(3) a fee determined in accordance with
19.10.2.203 NMAC; and
(4) the
annual fee shall be calculated each year based on cumulative acreage disturbed
as of December 31st of the prior year, and shall be due on or before April 30th
of each subsequent year following initial submittal of a permit
application.
C. The annual fee for a minimal impact existing mining operation shall be $250.00. This fee shall be due on or before April 30th of each year following initial submittal of permit application.
D. The annual fee for a minimal impact new mining operation shall be $250.00. This fee shall be due on or before April 30th of each year following initial submittal of permit application.
E. Formula for reducing fees for substantially reclaimed acreage.
(1) For the purposes of 19.10.2 NMAC,
"substantially reclaimed" means financial assurance has been released pursuant
to 19.10.12.1210 NMAC except the amount to establish revegetation pursuant to
Subsection A of 19.10.12.1204 NMAC.
(2) For the purposes of 19.10.2 NMAC, the
total annual pre-reclamation fee is the total annual fee calculated assuming no
reclamation has taken place.
(3)
Base fees, disturbance fees and facility fees calculated pursuant to Subsection
A of 19.10.2.202 NMAC or Subsection B of 19.10.2.202 NMAC shall be reduced in
proportion to the area substantially reclaimed as compared to the total
pre-reclamation fee but shall not be reduced to less than 60 percent of the
total annual pre-reclamation fee. Formula for fee calculation: Fee owed =
pre-reclamation fee - (AR/AT) * (pre-reclamation fee), where AT = total acreage
and AR = reclaimed acreage.
Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.