A. A conservation project involving acquisition of a conservation or agricultural easement requires an appraisal that establishes the fair market value of the conservation or agricultural easement and meets United States treasury regulations and the uniform standards of professional appraisal practice before the department will disburse the funds to the qualified entity.
B. In addition, for conservation projects involving acquisition of a conservation or agricultural easement, the qualified entity or partner conservation entity shall provide as specified by the department documents including a title commitment; phase I environmental site assessment and, if needed based on phase I environmental site assessment, a phase II environmental site assessment; a title opinion certifying that the landowner owns the minerals rights or a report, satisfactory to the department, from a professional geologist that the probability of surface mining occurring on such property is so remote as to be negligible; and if deemed necessary by the department, a property boundary survey. If the landowner owns the mineral rights, an easement shall prohibit subsequent sale or development of mineral rights by the landowner granting the conservation or agricultural easement. A baseline documentation report of the property shall be recorded with the deed of conservation easement or agricultural easement in the office of the applicable county clerk.
C. Agricultural and conservation easements shall contain a provision that if a qualified entity, other than the department, or a partner conservation entity fails to enforce the easement as determined by a court or if either the qualified entity or conservation entity cease to exist, that the easement will go to another qualified entity or partner conservation entity as specified in the easement and agreed to by that qualified entity, or otherwise the easement shall become vested in the department as recommended by the department and other extant easement right holders. Any qualified entity's interest in an easement shall only go to another governmental entity. The department shall have the option to provide similar rights of enforcement or possession to other governmental entities (e.g., federal partners) where such partners have similar rules, regulations or requirements and demonstrated capacity to manage or enforce easements.
D. Grant awards may be approved for use to pay transactional costs for easement projects such as appraisals, title insurance, title opinions, surveys or environmental reviews up to three percent of the total value of the conservation project funded or 10 percent of the amount of the grant, whichever is less. The committee and the department may consider and approve grant requests for paying only transaction costs for easement projects, subject to the grant being for up to three percent of the total value of the conservation project or $45,000, whichever is less.
E. Overhead and administrative expenses used as in-kind contributions may be no more than 10 percent of the total cost of a project.
F. A qualified entity or conservation entity may use contractors or subcontractors so long as their use is explained in the application, all applicable procurement requirements are met and the contractors or subcontractors are identified by name in the application, to the extent known. If contractors or subcontractors are identified in the application, the qualified entity or entities shall include documentation in the application that demonstrates all applicable procurement requirements were met. The qualified entity or entities associated with an approved project shall be wholly responsible for the project execution and performance, whether or not contractors or subcontractors are used. Use of contractors or subcontractors not identified in an application shall require the department's prior written approval.
G. Prior to commencing any work, any contractors or subcontractors may be required to furnish state certification from insurers for coverage in the minimum amounts as designated by the state. Appropriate coverage shall be maintained in full force and effect during the term of the project and shall not serve to limit any liabilities or any other contractor obligations. The state and the department must be added as additional insured as required by statute, agreement or other obligation.