A. A UFO shall report to the director or pipeline safety bureau any incident in which the owner or operator's underground facility is damaged by excavation activities. Such report, where practicable, shall be submitted using the commission's website at: http://nmprc.state.nm.us/transportation/pipeline-safety.html. For purposes of this subsection, incident is to be taken in its general sense and is not to be restricted to the definition given in 49 CFR 191.3.
B. The report shall be filled out in its entirety and should include any and all information, such as pre-dig and post-damage photos, the UFO used to determine probable cause and support or justifies its position.
C. The report shall be submitted within 30 calendar days of occurrence. Any additional information provided after the 30 day deadline may be considered on a case by case basis.
D. The UFO shall make available to the director or staff, within a reasonable time, such other information or documentation as the director or staff may require regarding any damage reportable under this section.