New Mexico Administrative Code
Title 18 - TRANSPORTATION AND HIGHWAYS
Chapter 28 - HIGHWAY CONTRACTING AND BIDDING
Part 6 - TRANSPORTATION CONSTRUCTION MANAGER GENERAL CONTRACTOR RULE
Section 18.28.6.11 - AWARD OF CONTRACTS
Current through Register Vol. 35, No. 18, September 24, 2024
Nothing in this rule requires the department to award a contract during either of the contract phases.
A. The basis for selection for award of contract shall be stated in the RFP and may be based on any of the following approaches:
B. The second phase construction services contract may be awarded after the project plans have been sufficiently developed and the GMP for construction services has been successfully validated and accepted by the department.
C. In the event a GMP is not validated and accepted, the department may:
D. If the department proceeds to award the second phase construction services contract through the competitive sealed bid process, the CMGC is prohibited from bidding.