Current through Register Vol. 35, No. 18, September 24, 2024
A. Relationship to other commission rules. The standards and procedures for the interconnection of qualifying facilities subject to this section (17.9.570.14 NMAC) are set forth in 17.9.568 NMAC.
B. Use of a single meter. When the customer is billed under a rate structure that does not include time-of-use energy pricing, a single energy meter shall be used to implement net metering of a qualifying facility unless an alternate metering arrangement is agreed to by the customer and utility. If either the utility or the customer requests an alternate form of metering or additional metering that is not required to accomplish net metering or is for the convenience of the party, the party requesting the change in metering shall pay for the alternate or additional metering arrangement. If the customer elects to take electric service under any rate structure, including time-of-use, that requires the use of metering apparatus or a metering arrangement that is more costly than would otherwise be necessary absent the requirement for net metering, the customer shall be required to pay the additional incremental cost of the required metering equipment. Within ten days of receiving notification from the customer of the intent to interconnect, the utility will notify the customer of any metering costs. Charges for special metering costs shall be paid by the customer, or arrangements for payment agreed to between the customer and utility, prior to the utility authorizing interconnected operation.
C. Net metering calculation. The utility shall calculate each customer's bill for the billing period using net metering and with the following conditions: