New Mexico Administrative Code
Title 17 - PUBLIC UTILITIES AND UTILITY SERVICES
Chapter 9 - ELECTRIC SERVICES
Part 568 - INTERCONNECTION OF GENERATING FACILITIES WITH A NAMEPLATE RATING UP TO AND INCLUDING 10 MW CONNECTING TO A UTILITY SYSTEM
Section 17.9.568.26 - EXTENSIONS

Universal Citation: 17 NM Admin Code 17.9.568.26

Current through Register Vol. 35, No. 18, September 24, 2024

A. The applicant may request in writing the extension of one timeline set by these rules. The requested extension may be for up to one-half of the time originally allotted (e.g., a 10 business day extension for a 20 business day timeframe). The utility shall not unreasonably refuse this request.

B. If further timeline extensions are necessary, the applicant may request an extension and the utility shall grant the extension so long as it does not unreasonably delay the processing of later queued interconnection applications.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.