New Mexico Administrative Code
Title 17 - PUBLIC UTILITIES AND UTILITY SERVICES
Chapter 9 - ELECTRIC SERVICES
Part 568 - INTERCONNECTION OF GENERATING FACILITIES WITH A NAMEPLATE RATING UP TO AND INCLUDING 10 MW CONNECTING TO A UTILITY SYSTEM
Section 17.9.568.18 - DETAILED STUDY PROCESS

Universal Citation: 17 NM Admin Code 17.9.568.18

Current through Register Vol. 35, No. 18, September 24, 2024

A. Application: An interconnection customer must submit an interconnection application, pursuant to Subsection B of 17.9.568.13 NMAC, using the interconnection application form for fast track and detailed study provided in Appendix 1C, which may be sent electronically to a recipient designated by the utility. The application fee specified in Subsection A of 17.9.568.23 NMAC shall be submitted along with the application. An applicant who was unable to proceed through the simplified or fast track process application due to failure of the screening process may request that the utility treat that existing interconnection application as a new detailed study application.

B. Scoping meeting:

(1) A scoping meeting will be held within 10 business days after the interconnection application is deemed complete., or the applicant agrees to proceed to detailed study after simplified or fast track review or as otherwise mutually agreed to by the parties. By mutual agreement of the parties, the scoping meeting, system impact study or facilities study may be waived. The utility and the applicant will bring to the meeting personnel, including system engineers and other resources as may be reasonably required to accomplish the purpose of the meeting.

(2) The purpose of the scoping meeting is to discuss the interconnection application, the reference point of applicability, and review existing studies relevant to the interconnection application. The parties shall further discuss whether the utility should perform a feasibility study (at the customer's option) or proceed directly to a system impact study, or a facilities study, or an interconnection agreement. If the parties agree that a feasibility study should be performed, the utility shall provide the applicant, as soon as possible, but not later than five business days after the scoping meeting, a feasibility study agreement, provided by the utility, including an outline of the scope of the study and a non-binding, good- faith estimate of the cost to perform the study.
(a) the feasibility study will provide a preliminary review of short circuit currents, including contribution from the proposed generation facility, and coordination and potential overloading of distribution circuit protection devices. If the interconnection applicant agrees to the feasibility study, the interconnection applicant shall provide an executed agreement and a deposit for the estimated costs provided by the utility;

(b) the scope of the feasibility study can be modified by the parties upon mutual agreement.

(3) In order to remain in consideration for interconnection, an applicant who has requested a feasibility study must return the executed feasibility study agreement and any required deposit within 15 business days. If the parties agree not to perform a feasibility study, the utility shall provide the applicant, no later than five business days after the scoping meeting, a system impact study agreement provided by the utility including an outline of the scope of the study and a non-binding, good faith estimate of the cost to perform the study.

C. Feasibility study: A feasibility study shall identify any potential adverse system impacts that would result from interconnection of the generating facility.

(1) A deposit of the lesser of fifty percent of the good faith estimated feasibility study cost, or earnest money of $1,000.00 may be required by the utility.

(2) Once the feasibility study is completed, a feasibility study report shall be prepared and transmitted to the applicant. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted within 30 business days of the applicant's agreement to conduct a feasibility study.

(3) If the feasibility study shows no potential for adverse system impacts, but facilities are required, the utility shall send the applicant a facilities study agreement, including an outline of the scope of the study and a non-binding, good faith estimate of the cost to perform the study.

(4) If no additional facilities are required, the utility shall provide the applicant an executable interconnection agreement within five business days.

D. System impact study: A system impact study shall identify and detail the electric system impacts that would result if the proposed generating facility were interconnected without project modifications or electric system modifications. A system impact study shall consist of a short circuit analysis, a stability analysis, a power flow analysis, voltage drop and flicker studies, protection and set point coordination studies, and grounding reviews, as necessary. A system impact study shall state the impact of assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. A system impact study shall provide a list of facilities that are required as a result of the interconnection application and non-binding good faith estimates of cost responsibility and time to construct. The system impact study must take into account the proposed generating facility's design and operating characteristics, including but not limited to the proposed operating profile, and study the generating facility according to how it is proposed to be operated. If the generating facility limits export pursuant to 17.9.568.12 NMAC, the system impact study must use export capacity instead of the nameplate rating, except when assessing fault current contribution. To assess fault current contribution, the system impact study must use the rated fault current; for example, the customer may provide manufacturer test data (pursuant to the fault current test described in IEEE 1547.1-2020 clause 5.18) showing that the fault current is independent of the nameplate rating.

(1) The utility shall provide the applicant a system impact study agreement within five business days if:
(a) a feasibility study is conducted and indicates adverse impacts on either the transmission system or the distribution system;

(b) the parties agree at the scoping meeting to proceed directly to a system impact study;

(c) the scoping meeting is omitted by mutual agreement; or

(d) the simplified process or fast track process has been completed and the applicant has elected to continue with the study process, and a system impact study is required.

(2) The system impact study agreement shall include an outline of the scope of the study and a non-binding good-faith estimate of the cost to perform the study. If applicable, the agreement shall list any additional and reasonable technical data on the generating facility needed to perform the system impact study. The scope of and cost responsibilities for a system impact study must be described in the system impact study agreement. A deposit of the good faith estimated costs for each system impact study shall be provided by the applicant when it returns the study agreements. The additional and reasonable technical data, if applicable, shall be returned with the system impact agreement. In order to remain under consideration for interconnection, the applicant must return the executed system impact study agreements and a deposit for the good-faith estimates of the studies within 20 business days.

(3) If the feasibility study shows no potential for adverse impacts on either the transmission or distribution systems, (or the parties agree to proceed straight to a facilities study), the utility shall send the applicant a facilities study agreement, including an outline of the scope of the study and a non-binding, good faith estimate of the cost to perform the study, or an executable interconnection agreement, as applicable.

(4) A system impact study shall be completed within 40 business days after the system impact study agreement is signed by the parties and delivered with deposit to the utility. The results and, if necessary, facilities study agreement shall be delivered to the applicant within five business days of completion of the system impact study. Upon request, the utility shall provide the applicant supporting documentation and workpapers developed in the preparation of the system impact study.

(5) In instances where the system impact study shows potential for transmission system adverse system impacts, within five business days following the identification of such impacts by the utility, the utility shall coordinate with the appropriate transmission provider to have the necessary studies completed to determine if the DER causes any adverse transmission impacts. If the utility's transmission service agreement requires that the transmission provider be notified of an interconnection, it shall provide that notice, regardless of whether the system impact study shows potential for transmission system adverse system impacts, and coordinate with the transmission provider on any studies it may determine are necessary.

(6) In order to remain in consideration for interconnection, an applicant must return the executed transmission system impact study agreement within 15 business days of receipt of the agreement.

(7) A transmission system impact study, if required, shall be completed and the results transmitted to the applicant in as timely a manner as possible after the transmission system impact study agreement is signed by the parties. The utility shall be responsible for coordination with the transmission provider as needed. Affected systems shall participate in the study and provide all information necessary to prepare the study.

(8) A one-time modification of the interconnection application is allowed as a result of information from the system impact study report.
(a) if the applicant chooses to amend the interconnection application to address the specific system impacts, the applicant must submit an updated interconnection application demonstrating the redesign within 15 business days after receiving the system impact study results from the utility. The redesign shall only include changes designed to address the specific system impacts or identified upgrades (which could include, for example, the addition of DC-coupled or AC-coupled energy storage). This redesign option to mitigate impacts shall only be available one time during the detailed study process. Increases in export capacity or changes in point of interconnection are not permitted and shall require the interconnection application to be withdrawn and resubmitted;

(b) the utility shall notify the interconnecting customer within ten business days of receipt of the modified interconnection application if any additional information is needed. If additional information is needed or document corrections are required, the applicant shall provide the required information or corrections within 10 business days from receipt of the utility notice;

(c) the actual costs to the utility for any necessary restudies as a result of a modification described above shall be paid by the applicant. Such restudies should be limited to the impacts of the modification and shall be billed to the applicant at cost and not for work previously completed. The utility shall use reasonable efforts to limit the scope of such restudies to what is necessary. The revised impact study shall be completed within 15 business days.

E. Facilities study: Once the required system impact study/studies are completed, a system impact report shall be prepared and transmitted to the applicant along with a facilities study agreement within five business days.

(1) The report and agreement shall provide an outline and non-binding, good faith estimate of the cost of the facilities study.

(2) In order to remain under consideration for interconnection, the applicant must return the executed facilities agreement, and a deposit for the good-faith estimates of the studies, within 15 business days. The facilities study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s).

(3) Design for any required interconnection facilities or upgrades shall be performed under the facilities study agreement. The utility may contract with consultants to perform activities required under the study agreement.

(4) The applicant and the utility may agree to allow the applicant to arrange for the design of some of the interconnection facilities, but the proposed deign will be reviewed subject to modification by the utility prior to acceptance.

(5) In cases where upgrades are required, the facilities study must be completed within 45 business days of the receipt of the executed facilities study agreement and deposit. In cases where no upgrades are necessary, and the required facilities are limited to interconnection facilities, the facilities study must be completed within 30 business days of the receipt of the executed facilities study agreement and deposit.

(6) Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the applicant. Upon request, the utility shall provide applicant supporting documentation and workpapers developed in the preparation of the interconnection facilities study.

(7) Upon completion of the facilities study, and with the agreement of the interconnection applicant to pay for interconnection facilities or upgrades identified in the study, the utility shall provide the interconnection applicant with an executable interconnection agreement within five business days.

F. Payment for study costs: For each of the studies conducted, any study fees shall be based on the utility's actual costs and will be invoiced to the applicant after the study is completed and delivered and will include a summary of professional time. The applicant must pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund such excess within 30 calendar days of the invoice without interest.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.