New Mexico Administrative Code
Title 17 - PUBLIC UTILITIES AND UTILITY SERVICES
Chapter 9 - ELECTRIC SERVICES
Part 568 - INTERCONNECTION OF GENERATING FACILITIES WITH A NAMEPLATE RATING UP TO AND INCLUDING 10 MW CONNECTING TO A UTILITY SYSTEM
Section 17.9.568.13 - APPLICATION REVIEW PROCESS

Universal Citation: 17 NM Admin Code 17.9.568.13

Current through Register Vol. 35, No. 18, September 24, 2024

A. There are four interconnection review paths:

(1) Simplified process: For certified inverter-based generating facilities that have a nameplate rating that does not exceed 50 kilowatts (kW) and an export capacity that does not exceed 25 kilowatts (kW).

(2) Fast track process: For generating facilities that have a nameplate rating of up to 5 megawatts (MW), depending on the line capacity and distance from the substation. To qualify for fast track, the generating facility's export capacity shall not exceed the limits identified in the table below, which vary according to the voltage of the line at the proposed point of interconnection. Generating facilities located within 2.5 miles of a substation and on a main distribution line with minimum 600-amp capacity are eligible for the fast track process under higher thresholds. For purposes of the table below, a mainline is the three-phase backbone of a circuit. It will typically constitute lines with wire sizes of 4/0 American wire gauge, 336.4 kcmil, 397.5 kcmil, 477 kcmil and 795 kcmil.

Line Voltage

Export Capacity for Fast Track Eligibility

Regardless of location

On > 600 amp line and < 2.5 miles from substation

5 kV

< 500 kW

< 500 kW

5 kV - 14 kV

< 2 MW

< 3 MW

15 kV - 30 kV

< 3 MW

< 4 MW

31 kV - 69 kV

< 4 MW

< 5 MW

(3) Detailed study process: For all generating facilities with a rated capacity 10 megawatts (MW) or less that do not qualify, or pass through, the simplified or fast track processes or subsequent supplemental review.

(4) Case specific review process: Generating facilities with a rated capacity greater than 10 megawatts (MW) shall be reviewed pursuant to 17.9.569 NMAC.

B. Application submittal: The interconnection applicant shall submit an interconnection application (see Appendices 1A, 1B or 1C, as appropriate) to the utility, together with the applicable processing fee identified in 17.9.568.23 NMAC. The application shall be date and time-stamped upon receipt for the purposes of any timetable in these procedures

C. Completeness review: Utility shall notify the interconnection applicant, via email or other means, that the interconnection application has been received within three business days of receipt of the interconnection application. Within 10 business days of receipt, the utility shall notify the applicant whether the interconnection application is deemed complete and valid. If the application is incomplete, the utility shall provide the applicant with a list of all information that the applicant must provide to complete the application. The applicant must provide the requested information within 10 business days, or the application will be deemed withdrawn.

D. Interconnection queue position and posting: The utility shall assign the interconnection application a queue position based on when it is received under Subsection C of 17.9.568.13 NMAC.

(1) The utility shall maintain a single queue, which may be sortable by geographic region (e.g., feeder or substation).

(2) The queue position of each interconnection application will be used to determine the cost responsibility for the upgrades necessary to accommodate the interconnection.

(3) The queue shall be publicly available on the utility's website and shall be updated at least monthly.

(4) If an application fails the screening process under the simplified or fast track process, but the applicant decides to continue with review (including Supplemental review) under another level, the applicant shall retain its original queue position.

(5) If an interconnection application fails the screening process under the simplified or fast track process, but the applicant decides to continue with review (including supplemental review) under another level, the applicant shall retain its original queue position.

E. Modifications to generating facility:

(1) At any time after an interconnection application is deemed complete or an interconnection agreement has been signed, if the applicant wishes to make modifications to the planned generating facility it shall submit to the utility, in writing, all proposed modifications to any information provided in the interconnection application or in the interconnection agreement. Any modification to machine data, equipment configuration, or to the interconnection site of the generating facility not agreed to in writing by the utility and the interconnection customer may be deemed a withdrawal of the interconnection application.

(2) Within 10 business days of receipt of a proposed modification, the utility shall notify the applicant whether a proposed modification to either an interconnection application or an existing generating facility constitutes a material modification.
(a) If the utility determines the proposed modification is a material modification, then the utility shall notify the interconnection customer in writing that the customer may:
(i) withdraw the proposed modification; or

(ii) proceed with a new interconnection application for such modification. The interconnection customer shall provide its determination in writing to the utility within 10 business days after being provided the material modification determination results. If the interconnection customer does not provide its determination, the proposed modification shall be deemed withdrawn.

(b) If the proposed modification is determined not to be a material modification, then the utility shall notify the interconnection customer in writing that the modification has been accepted and that the customer shall retain its eligibility for interconnection, including its place in the interconnection queue. Existing generating facilities may make the modification without requiring a new interconnection application.

(3) Any dispute as to the utility's determination that a modification constitutes a material modification shall proceed in accordance with the dispute resolution provisions in 17.9.568.26 NMAC.

(4) Any modification to machine data, equipment configuration, or to the interconnection site of the generating facility not agreed to in writing by the utility and the interconnection customer may be deemed a withdrawal of the interconnection application and may require submission of a new interconnection application, unless proper notifications of each party by the other as described in Paragraphs (1) and (2) of Subsection E of 17.9.568.13 NMAC.

F. Site Control: Documentation of site control must be submitted with the interconnection request. Site control may be demonstrated by:

(1) ownership of, or a leasehold interest in, or a right to develop a site for the purpose of constructing a generating facility;

(2) a fully executed option to purchase or acquire a leasehold site for such purpose; or

(3) a fully executed agreement demonstrating exclusivity or other business relationship between the interconnection applicant and the entity having the authority to grant the applicant the right to possess or occupy a site for such purpose.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.