New Mexico Administrative Code
Title 17 - PUBLIC UTILITIES AND UTILITY SERVICES
Chapter 11 - TELECOMMUNICATIONS
Part 18 - INTERCONNECTION FACILITIES AND UNBUNDLED NETWORK ELEMENTS
Section 17.11.18.20 - ARBITRATION OF INTERCONNECTION AGREEMENTS
Current through Register Vol. 35, No. 18, September 24, 2024
A LEC that is unable to negotiate an interconnection agreement with an ILEC may petition the commission to arbitrate any unresolved issues.
A. To initiate arbitration, a LEC shall:
B. The ILEC may, within twenty-five (25) days after it receives the petition, respond to the LEC's petition and provide additional information to the LEC and the commission.
C. The commission shall resolve all issues presented to it within nine months from the date the ILEC received the request for interconnection.
D. The commission shall approve or reject the arbitrated agreement in accordance with the standards prescribed in 47 U.S.C. Section 252(e) and all of its subparts within thirty (30) days after its submission by the parties.