New Mexico Administrative Code
Title 17 - PUBLIC UTILITIES AND UTILITY SERVICES
Chapter 1 - UTILITIES GENERAL PROVISIONS
Part 3 - FUTURE TEST YEAR PERIOD FILING REQUIREMENTS IN SUPPORT OF RATE SCHEDULES FOR INVESTOR-OWNED UTILITIES
Section 17.1.3.10 - VARIANCES
Current through Register Vol. 35, No. 18, September 24, 2024
A. Pursuant to 17.1.2 NMAC and 17.1.210 NMAC, a utility unable to comply fully with any data request contained in this rule due to good and sufficient cause shall give notice in writing to the commission of the utility's inability to comply with the provisions of such data request at least 30 days prior to the actual filing of the minimum data requirements filing package.
B. Upon receipt of such notification and after consideration by the commission of the utility's stated reasons for failure to comply fully with the provisions of the data request, the commission shall within 15 days notify the utility in writing of its decision concerning the utility's notice of its inability to comply with the commission's data filing requirements.