See this Chapter of the IECC except as provided below.
A. Section C401 General. See this section of the IECC except as provided below. Section C401.3 Thermal envelope certificate. Delete this section of the IECC.
B. Section C402 Building envelope requirements. See this section of the IECC except as provided below. Section C402.4.2.1 Lighting controls in toplit daylight zones. Delete this section of the IECC without substitution.
C. Section 403 Building mechanical systems. See this section of the IECC except as provided below. Section C403.7.1 Demand control ventilation. See this section of the IECC except delete "Table 403.3.1.1 of the International mechanical code" and replace with "Table 402.1 of the uniform mechanical code" wherever referenced in this section.
D. Section 405 Electrical power and lighting systems. See this section of the IECC except as provided below.
Exception: Parking facilities, serving occupancies other than R-2 with fewer than 10 automobile parking spaces.
TABLE C405.13.1 REQUIRED EV POWER TRANSFER INFRASTRUCTURE
Occupancy |
EVSE Spaces |
*EV Capable Spaces |
Group A |
5% |
10% |
Group B |
5% |
5% |
Group E |
5% |
5% |
Group F |
2% |
5% |
Group H |
1% |
0% |
Group I |
5% |
10% |
Group M |
5% |
10% |
Group R-1 |
5% |
15% |
Group R-2 |
5% |
15% |
Group R-3 and R-4 |
2% |
5% |
Group S exclusive of Parking Garages |
1% |
0% |
Group S-2 Parking Garages |
5% |
10% |
*EVCapable Spaces are in addition to the required EVSE Spaces.
D. Section C408 Maintenance Information and System Commissioning. See this section of the IECC except as provided below.
Exceptions: The following systems are exempt:
FIGURE C408.2.4
COMMISSIONING COMPLIANCE CHECKLIST
Project Information: ________________________________ Project Name:__________________________
Project Address: _________________________________________________________________________
Commissioning Authority: __________________________________________________________________
Commissioning Plan (Section C408.2.1)
[] Commissioning Plan was used during construction and includes all items required by Section C408.2.1
[] Systems Adjusting and Balancing shall be completed per plans and specifications.
[] HVAC Equipment Functional Testing shall be completed per plans and specifications.
[] HVAC Controls Functional Testing shall be completed per plans and specifications.
[] Economizer Functional Testing shall be completed per plans and specifications.
[] Lighting Controls Functional Testing shall be completed per plans and specifications.
[] Service Water Heating System Functional Testing shall be completed per plans and specifications.
[] Manual, record documents and training shall be completed per plans and specifications.
[] Preliminary Commissioning Report shall be submitted to the owner and includes all items required by Section C408.2.4.
[] The above-referenced items are scheduled to be provided on:
I, the commissioning provider, do hereby certify that I am providing the owner or owner's representative with documentation as to the mechanical, service water heating and lighting systems commissioning in accordance with the 2021 IECC.
_____________________________________________ ____________________
Signature of Commissioning Provider Date
____________________________________________ ____________________
Signature of Building Owner/Owner's Representative Date
_____________________________________________________________________________