New Mexico Administrative Code
Title 14 - HOUSING AND CONSTRUCTION
Chapter 5 - CONSTRUCTION INDUSTRIES GENERAL PROVISIONS
Part 3 - INSPECTIONS
Section 14.5.3.15 - CONNECTION APPROVAL

Universal Citation: 14 NM Admin Code 14.5.3.15

Current through Register Vol. 35, No. 18, September 24, 2024

A. Plumbing. No person shall connect, or reconnect, any plumbing system to an energy or water source or to a sewer system until the AHJ or appropriate inspector has given approval to do so.

B. Mechanical. No person shall connect, or reconnect, any mechanical system or equipment to an energy, fuel or other power source until the AHJ or appropriate inspector has given approval to do so.

C. Electrical. No person shall connect, or reconnect any electrical wiring to an energy source until the AHJ building official or appropriate inspector has given approval to do so.

D. Exception. A public or private utility may make a connection from a supply of water or gas to an installation if, the appropriate AHJ has failed to approve or disapprove the work or installation to which the connection will be made within seven working days after receiving notification that the work is ready to inspect.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.