Section 1.4.1.21 - LATE BIDS, LATE WITHDRAWALS AND LATE MODIFICATIONS

Universal Citation: 1 NM Admin Code 1.4.1.21

Current through Register Vol. 35, No. 18, September 24, 2024

A. Definition: Any bid or any withdrawal or modification of a bid received after the time and date for opening of bids at the place designated for opening is late. (NOTE: if the time a bid is due is listed as "3 p.m." this means 3:00:00 and not 3:00:59.)

B. General rule: No late bid, late modification, or late withdrawal will be considered unless received before contract award, and the bid, modification, or withdrawal would have been timely but for the action or inaction of state personnel directly serving the procurement activity.

C. Records: All documents relating to late bids, late modifications, or late withdrawals shall be made a part of the appropriate procurement file.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.