Section 1.12.5.11 - REPORTING REQUIREMENTS

Universal Citation: 1 NM Admin Code 1.12.5.11

Current through Register Vol. 35, No. 18, September 24, 2024

A. Project status reports. For all projects that require office oversight, the lead agency project manager shall submit an agency approved project status report on a monthly basis to the office.

B. Independent verification and validation assessment reporting. The office requires all projects subject to oversight to engage an independent verification and validation contractor unless waived by the office. The IV&V contractor shall perform the following activities.

(1) Prepare an initial risk assessment report at project inception. This assessment will include recommended mitigation activity to reduce the impact and probability of the identified risk.

(2) Prepare initial status report at project inception to disclose the effectiveness of project management and whether the documented project activities are meeting the objectives set forth by project.

(3) Prepare interim reports based on the phases as indicated within the project schedule. Included in the report will be an evaluation on whether product development requirements are being met, project management is effective, continuing risk analysis, and how the project is implementing previous recommended risk mitigation strategies.

(4) Prepare a post implementation assessment at project close to indicate whether project objectives were met based on the project's scope and acceptance criteria.

(5) Submit each risk assessment report, status report, interim report, and post-implementation assessment report to the office within five (5) business days of each deliverable due date as indicated on the project schedule. All reports must be submitted to the agency heads and the office.

Disclaimer: These regulations may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.