New Jersey Administrative Code
Title 9A - HIGHER EDUCATION
Chapter 6 - USE OF DESIGN-BUILD PROJECT DELIVERY FOR CONSTRUCTION PROJECTS
Subchapter 1 - USE OF DESIGN-BUILD PROJECT DELIVERY FOR CONSTRUCTION PROJECTS
Section 9A:6-1.12 - Disclosure; access and record retention
Current through Register Vol. 56, No. 18, September 16, 2024
(a) Any and all submissions made in response to any RFQ and any RFP are subject to the provisions of the Open Public Records Act, N.J.S.A. 47:1A-1 et seq., and the exceptions from disclosure provided therein, except that technical proposals shall not be subject to disclosure prior to award of the contract.
(b) The design-builder awarded a design-build contract shall make available records and accounts pertaining to the design-build project to the Office of the State Comptroller in any investigations, examinations, and inspections that they may undertake of the activities related to the financing and undertaking of design-build projects. The design-builder shall also cooperate, upon request, in sharing information with other State or Federal entities.
(c) The design-builder and contracting unit shall retain all records and accounts, including records and accounts of subcontractors and subconsultants, for design-build project activities, as necessary, to evidence compliance with the Act and all applicable regulations and contractual requirements. Such records shall be retained for 10 years following substantial completion of a design-build project, and any additional period required for the resolution of litigation, claims, or audit findings. At any time, upon request of the Secretary of Higher Education, the contracting unit and the design-builder shall make records relating to the design-build project available to the Secretary within four business days of the request for documents and at no cost.
(d) In the event that any litigation, claim, audit, or request pursuant to the Open Public Records Act, N.J.S.A. 47:1A-1 et seq., relating to the procurement or the performance of work under the design-build contract is commenced prior to expiration or termination of the design-build contract, all records relating to the procurement and the contract shall be retained until all litigation, claims, audit findings, document requests, and related appeals, if any, have been resolved with finality.