(a) For each project that is subject to review by the Commission for stream corridor impact in accordance with N.J.A.C. 7:45-9.1, the applicant shall submit to the Commission a map of the project site delineating the stream corridor at a scale of one inch equals 100 feet and containing the following:

1. The 100-year flood line, verified by the Department's Division of Land Use Regulation;

2. The 100-foot wide buffer along the 100-year flood line;

3. The location of all improvements and/or disturbances proposed to be located within the stream corridor;

4. A description of existing vegetation in the stream corridor; and

5. A metes and bounds description of the project site boundary and the stream corridor boundary, both on hard copy as well as a digital rendition, either as a CAD.dxf file or ArcView shapefile.

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.