Section 7:36-14.6 - Project closeout
Current through Register Vol. 56, No. 18, September 16, 2024
(a) The local government unit shall notify Green Acres when the development project is complete.
(b) Upon receipt of the notification under (a) above, Green Acres shall send to the local government unit a project closeout letter that directs the local government unit to submit to Green Acres a copy of each of the following:
(c) Green Acres shall conduct a final site inspection within 45 days of its receipt of the items listed under (b) above.
(d) Green Acres shall provide to the local government unit a sign (or signs, as applicable) that identifies the parkland as a Green Acres funded site that is permanently dedicated to recreation and conservation purposes. The local government unit shall post the sign(s) in a prominent place on the funded parkland and maintain it.