New Jersey Administrative Code
Title 7 - ENVIRONMENTAL PROTECTION
Chapter 24A - DAM RESTORATION AND INLAND WATERS PROJECTS LOAN PROGRAM
Subchapter 4 - PROJECT IMPLEMENTATION PHASE
Section 7:24A-4.2 - Loan conditions
Universal Citation: NJ Admin Code 7:24A-4.2
Current through Register Vol. 56, No. 24, December 18, 2024
(a) The following requirements, in addition to the requirements of such other statutes, rules, terms and conditions as may be applicable to a particular loan, are conditions of each loan and conditions precedent to each disbursement under a loan award agreement:
1. No
disbursement shall be made under a loan award agreement until a specific
appropriation therefore has been made by the Legislature.
2. The borrower shall certify that the
project or phase of the project was initiated and completed in accordance with
the time schedule specified in the loan award agreement.
3. The borrower shall certify that the
borrower and its contractors and subcontractors shall comply with all insurance
requirements of the loan award agreement and certify, when appropriate, that
the insurance is in full force and effect and that the premiums have been paid.
The borrower shall include the State and its agencies, employees and officers
as additional named insureds on any certificate of liability insurance (or
other similar document evidencing liability insurance coverage) of the
contractor. The borrower shall provide the Department with a copy of the
certificate of liability insurance (or other similar document evidencing
liability insurance coverage) prior to proceeding with the project. Such
certificate shall be maintained in full force and represent a continuing
obligation to include the State and its agencies, employees and officers as
additional named insureds through the completion of construction. The borrower
shall not alter or cancel such certificate without prior notification to the
Department, in writing, 15 days in advance of any alteration or
cancellation.
4. The borrower shall
certify that the borrower and its contractors and subcontractors maintain their
financial records in accordance with
N.J.A.C. 7:24A-4.20.
5. The borrower shall certify that the
borrower and its contractors and subcontractors are in compliance with the
discrimination and affirmative action provisions of
N.J.S.A. 10:2-1 through
N.J.S.A. 10:2-4, the New Jersey Law Against
Discrimination,
N.J.S.A. 10:5-1 et seq., and the rules
promulgated pursuant thereto.
6.
The borrower shall certify that the borrower includes in all its construction
or development contracts for the project a requirement that the contractor post
a performance bond or other performance guarantee in an amount equal to the
full cost of the project.
i. The performance
bond or performance guarantee shall remain in effect until the Department
conducts its final inspection of the project and states in writing to the
applicant that the project is satisfactorily completed.
ii. The performance bond or performance
guarantee shall be both nondiscriminatory and financially satisfactory to the
Department, and meet all statutory requirements.
7. The borrower shall certify that the
borrower is in compliance with all other requirements and conditions of the
loan award agreement.
8. Bid
specifications shall require that project elements which constitute unallowable
project costs be bid as line items in the total bid specifications separate
from project elements which constitute allowable project costs.
9. Bid specifications shall require that each
general contractor who bids on the project shall identify in the bid submission
to the borrower the principal subcontractors.
10. Before the borrower makes any final award
of a construction contract, the borrower shall submit to the Department for
review and approval the final construction contract, with work specifications
detailing any changes made since submittal of the materials required during the
project development phase pursuant to N.J.A.C. 7:24A-3.
11. Concurrent with the submittal to the
Department required under (a)10 above, the borrower shall provide the
Department with a tabulation of bids received and identify the general
contractor to be awarded the construction contract for the project. In the
event a contract is not proposed to be awarded to the contractor who has
submitted the lowest bid, the borrower shall provide adequate justification for
said award.
12. The Department
reserves the right to require the borrower to readvertise the bid
specifications for the project if the Department deems the certifications
required in (a)13 below unsatisfactory.
13. The borrower shall certify the following
to the Department before the borrower awards any contract on a bid.
i. The borrower is in compliance with the
Local Public Contracts Law,
N.J.S.A. 40A:11-1 et seq., and the Local
Public Contracts rules, N.J.A.C. 5:34;
ii. All contracts for the project will be
awarded to the qualified, responsible and responsive bidder who submits the
lowest acceptable bid; and
iii. The
bid prices included in the bid specifications are reasonably
balanced.
14. The
borrower shall insert in all contracts or subcontracts that the borrower awards
pursuant to this chapter the Department's subcontractor certification form as
included in the loan award agreement.
15. The borrower shall submit one copy of the
executed construction contract and subcontracts and associated documents to the
Department within 10 days of their execution.
Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.