New Jersey Administrative Code
Title 7 - ENVIRONMENTAL PROTECTION
Chapter 20 - DAM SAFETY STANDARDS
Subchapter 1 - APPLICATION PROCEDURE; DESIGN CRITERIA FOR DAM CONSTRUCTION; DAM INSPECTION PROCEDURE
Section 7:20-1.9 - Design criteria
Current through Register Vol. 56, No. 18, September 16, 2024
(a) The minimum design storm used to calculate required spillway capacity must be determined according to the following table:
Hazard | Spillway Design Storm (SDS) |
Class I | PMP |
Class II | One-half PMP |
Class III | 24 hour 100 year frequency, |
Type III storm[1] | |
Class IV | 24 hour 100 year frequency, |
Type III storm plus 50%[1] |
[1] Any later technology adopted by the U.S. Department of Agriculture, Natural Resources Conservation Service may be substituted for the use of the Type III storm.
(b) For existing dams, it is recognized that the relationships between valley slope and width, total reservoir storage, drainage area, and other hydrologic factors have a critical bearing on determining the safe spillway design flood. When appropriate, based on the design of the dam, rational selection of a safe, reduced spillway design for specific site conditions based on quantitative and relative impact analysis is acceptable. The spillway should be sized so that the increased downstream damage resulting from overtopping failure of a dam would not be significant as compared with the damage caused by the flood in the absence of a dam overtopping failure. The minimum design storm for the dam shall be the 100 year storm.
(c) All Class II and III dams shall, where practicable, incorporate in the proposed design, the ability to make modifications necessary to increase the spillway capacity of the facility or other alternative measures if the downstream hazard potential increases.
(d) All dams shall have adequate storage for the design storm or have a spillway system which will safely pass the design storm without endangering the safety of the dam.
(e) Each spillway shall include a satisfactory means of dissipating the energy of flow at its outlet without endangering the safety of the dam.
(f) The capacity of the spillway system shall be equal to the peak inflow of the design flood unless the applicant demonstrates by flood routing procedures that the spillway system has the capacity to safely pass the resulting water flow.
(g) Pipe conduits may be used for the primary (principal) spillway. When so used, the following requirements shall be met:
(h) Should a vegetated or unlined auxiliary spillway, approved by the Department, be installed, it must be able to pass the design storm without jeopardizing the safety of the structure and that has a predicted average frequency of use less than:
(i) Drawdown requirements are as follows:
(j) Design references used shall be cited in the information submitted to the Department.
(k) Monitoring devices to permit inspection and assessment of the dam's condition may be required by the Department for use in the inspections during and after completion of construction.
(l) The applicant shall demonstrate to the Department that the riparian rights of downstream property owners will be protected during construction, during the period when the reservoir is being filled and during the life of the dam and reservoir.
(m) Unless the applicant can demonstrate that an alternative slope is acceptable, upstream slopes of an earth dam may be no steeper than three horizontal to one vertical ratio, and downstream slopes may be no steeper than two horizontal to one vertical ratio. Measures are required for protection of upstream slopes against wave action or rapid draw-down and for protection of the downstream slope against scour or erosion due to high tailwater.
(n) Freeboard requirements are as follows:
(o) The Department may require the design and installation of any additional or modified measures by any applicant for a dam permit where appropriate to insure the protection of human health or safety.