New Jersey Administrative Code
Title 7 - ENVIRONMENTAL PROTECTION
Chapter 14A - NEW JERSEY POLLUTANT DISCHARGE ELIMINATION SYSTEM
Subchapter 22 - TREATMENT WORKS APPROVALS, SEWER BANS, SEWER BAN EXEMPTIONS
Section 7:14A-22.5 - Treatment works approval
Current through Register Vol. 56, No. 18, September 16, 2024
(a) A treatment works approval consists of the following three stages:
(b) The construction, installation, modification or operation of a treatment works in a manner inconsistent with the terms and conditions of the Department's approval constitutes a violation of the Water Pollution Control Act, 58:10A-1 et seq. and may be subject to penalties and fines pursuant to the above Act, the Civil Administrative Penalty Rules, N.J.A.C. 7:14-8, or other applicable statute.
(c) The Department may modify, suspend or revoke a treatment works approval in accordance with 7:14A-22.11.
(d) A preapplication review is an optional service especially recommended for large-scale development. During this review the Department will discuss the apparent strengths and weaknesses of the proposed development, as well as the procedures and policies that would apply to the particular development. The conference is intended to provide guidance and does not constitute a commitment of approval or denial of a treatment works approval application for the proposed development.
(e) The Department shall approve, condition, or deny an application for a treatment works approval pursuant to this subchapter within 90 days of receipt of an administratively complete application by the Department. This time period may be extended for one 30-day period upon the mutual consent of the applicant and the Department.
(f) The issuance of a treatment works approval by the Department does not relieve the applicant of the continuing responsibility for the successful collection, conveyance, treatment or discharge of pollutants, nor does it relieve the applicant from the responsibility of insuring that all discharges are consistent at all times with the terms and conditions of the applicable NJPDES permit and that no pollutant will be discharged more frequently than authorized or at a level in excess of that which is authorized by the applicable NJPDES permit. The applicant is also responsible for complying with all applicable permits, regulations, statutes, or other laws.
(g) The applicant and any owner or operator of a treatment works shall provide notice of the terms and conditions of any existing treatment works approval to a prospective purchaser of the treatment works. Upon change of ownership of the treatment works, the new owner shall assume responsibility for its proper operation and maintenance or closure. Notification to the Department of a change in ownership for the treatment works approval permit is not required.
(h) The Department's review of applications and submissions is limited to engineering (including hydraulic) features of significance to applicable discharge limits and protection of the environment. The Department will not review structural, mechanical or electrical design, except when it may be significant to achievement of discharge limitations or to the protection of the environment.
(i) A permit to construct or operate a treatment works, previously issued to the owner or operator pursuant to N.J.S.A. 58:11-10 or 58:12-3 will constitute a treatment works approval for the purpose of this subchapter. The permit and any conditions thereto will continue to be in effect until such time as the permit is revoked, amended or expired.
(j) The full responsibility for adequate design, construction and operation of the treatment works, and the full responsibility for successful collection, treatment and discharge of pollutants shall be on the applicant.
(k) Treatment works shall be constructed in a manner which is consistent with the provisions of the appropriate wastewater management plan.
(l) The Department may grant an emergency approval authorizing the construction and/or operation of a treatment works prior to issuance of a formal treatment works approval in situations such as the modification/rehabilitation of existing treatment and conveyance systems where time delays may threaten the public health or safety. Such approvals shall be subject to the following requirements:
(m) For most industrial treatment works, treatment works approvals will be issued in the form of a General Industrial Treatment Works Approval. The submission requirements for a General Industrial TWA are contained in 7:14A-22.6, and are administrative in nature. Within 30 days of receipt of a complete General Industrial TWA application, the Department will issue a General Industrial TWA or notify the applicant that due to a potentially significant health risk, environmental impact, or past performance of the facility the project cannot be granted a General Industrial TWA and an individual treatment works approval is required.
(n) The Department shall publish in the DEP Bulletin, a report of the receipt of each new treatment works application and the final action taken. Publication in the DEP Bulletin constitutes constructive notice to all interested persons of the receipt by the Department of each new treatment works application and the final action taken by the Department on treatment works approvals.